DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.1 rate analysis

Providing and laying six courses water proofing treatment with bitumen felt over roofs consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45, 1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt type 2 grade I (fibre base self finished bitumen felt) six and final courses of stone grit 6 mm and down size or pea sized gravel spread at 6 cubic decimeter per sqm including preparation of surface, excluding grading, compete.

Published rate₹910.85DSR 2023
Rate analysis

Providing and laying six courses water proofing treatment with bitumen felt over roofs consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45, 1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt type 2 grade I (fibre base self finished bitumen felt) six and final courses of stone grit 6 mm and down size or pea sized gravel spread at 6 cubic decimeter per sqm including preparation of surface, excluding grading, compete.

DSR rate₹910.85as per item analysis
Item code
22.1
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
418

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 sqm
Blown bitumen applied hot
(1.45+1.20+1.70)x30 = 131 kg.
0313 Blown type petroleum bitumen of penetration 85/25 of approved quality tonne 0.131 ₹38,250.00 ₹5,010.75
Bitumen felt type B grade I (fibre base self finished bitumen felt) = 60 sqm. + Add for over lapping @ 10% = 6 sqm. Total =66 Sqm
0318 Bitumen felt fibre base (vegetable or animal):Type 2 grade 1 sqm 66 ₹75.00 ₹4,950.00
2211 Carriage of Tar bitumen tonne 0.278 ₹0.00 ₹0.00
I/c Hession felt =(0.131 t+2.22x.001x66 = 0.278t)
1177 Stone grit 6 mm and down size or pea sized gravel cum 0.18 ₹985.00 ₹177.30
30x6=180cudm
CARRIAGE:
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.18 ₹0.00 ₹0.00
Fuel (Steam coal) = 2 quintals/t of bitumen i.e. 2x0.131=0.262q
0370 Coal (steam) quintal 0.262 ₹500.00 ₹131.00
2200 Carriage of steam coal tonne 0.026 ₹0.00 ₹0.00
9999 Praparing roof surface, sutting groove and making good etc. L.S. 134.55 ₹2.27 ₹305.43
LABOUR
0131 Painter day 4.32 ₹816.00 ₹3,525.12
0114 Beldar day 6.48 ₹736.00 ₹4,769.28
0130 Mistry day 0.36 ₹897.00 ₹322.92
9999 Sundries, brushes etc. L.S. 6.76 ₹2.27 ₹15.35

Rate build-up

TOTAL ₹19,207.15
Add 1 % Water charges on "W" ₹192.07
TOTAL ₹19,399.22
Add GST on "X" (multiplying factor 0.2127) ₹4,126.21
TOTAL ₹23,525.43
Add 15% CPOH on "Y" ₹3,528.81
TOTAL ₹27,054.24
Add Cess @ 1% on "Z" ₹270.54
Cost of 30.00 Sqm. ₹27,324.78
Cost of 1.00 Sqm. ₹910.83
Say ₹910.85