DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.9.2 rate analysis

Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m. Hard rock (requiring blasting)

Published rate₹1,049.80per cum
Rate analysis

Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.

DSR rate₹1,049.80per cum

Hard rock (requiring blasting)

Item code
2.9.2
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
236

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
MACHINERY
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.125 ₹7,850.00 ₹981.25
0017 Hire and running charges of tipper day 0.125 ₹4,200.00 ₹525.00
LABOUR
0132 Rock Excavator day 1.24 ₹736.00 ₹912.64
0133 Rock Breaker day 3 ₹736.00 ₹2,208.00
0134 Rock Hole Driller day 1.06 ₹736.00 ₹780.16
0114 Beldar day 0.5 ₹736.00 ₹368.00
0115 Coolie day 1.3 ₹736.00 ₹956.80
0325 Blasting powder kilogram 6.42 ₹44.00 ₹282.48
0326 Blasting fuse (fuse wire) each 7 ₹46.00 ₹322.00
9999 Sundries L.S. 18.85 ₹2.27 ₹42.79

Rate build-up

TOTAL ₹7,379.12
Add 1 % Water charges on "W" ₹73.79
TOTAL ₹7,452.91
Add GST on "X" (multiplying factor 0.2127) ₹1,585.23
TOTAL ₹9,038.14
Add 15% CPOH on "Y" ₹1,355.72
TOTAL ₹10,393.86
Add Cess @ 1% on "Z" ₹103.94
Cost of 10 cum. ₹10,497.80
Cost of 1 cum. ₹1,049.78
Say ₹1,049.80