DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.33.1 rate analysis

Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. Beyond 30 cm girth upto and including 60 cm girth

Published rate₹532.35DSR 2023
Rate analysis

Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.

DSR rate₹532.35as per item analysis

Beyond 30 cm girth upto and including 60 cm girth

Item code
2.33.1
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
1894

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one tree of 15cm dia and average height 3m
LABOUR
quantity of wood-
3.14/4x0.15x0.15x3 = 0.053 cum.
Add 20% for branches = 0.011 cum.
Total = 0.064 cum.
Labour for cutting in trees removing the roots from the soil and then filling in Pit and depresions.
0114 Beldar day 0.33 ₹736.00 ₹242.88
0115 Coolie day 0.17 ₹736.00 ₹125.12
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹374.20
Add 1 % Water charges on "W" ₹3.74
TOTAL ₹377.94
Add GST on "X" (multiplying factor 0.2127) ₹80.39
TOTAL ₹458.33
Add 15% CPOH on "Y" ₹68.75
TOTAL ₹527.08
Add Cess @ 1% on "Z" ₹5.27
Cost of one tree ₹532.35
Say ₹532.35