DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.22.3 rate analysis

Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered): Depth exceeding 3 m but not exceeding 4.5 m

Published rate₹71.30per sqm
Rate analysis

Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered):

DSR rate₹71.30per sqm

Depth exceeding 3 m but not exceeding 4.5 m

Item code
2.22.3
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1472

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 area 30m long and 1.5m deep
area = 10x30 x 1.50 = 450 sqm.
MATERIAL
The Material can be used four times on the same work and after use of material credit is given @ 75% of cost
Polling boards of
1198 Second class kail wood in planks 10 cudm 35.625 ₹260.00 ₹9,262.50
250mm x 38mm
10x40x1.50x0.25x0.038 = 5.7cum. = 5700 dm³
Qty taken for cost of using once after
deducting for credit = 5700x¼x¼ = 356.25 dm³
Raking struts-
0302 Safeda ballies 125 mm diameter metre 37.5 ₹44.00 ₹1,650.00
10x40x1.50 = 600m
Qty taken for cost of using once after
deducting for credit = 600x¼x¼ = 37.5 m
2204 Carriage of Timber cum 3.275 ₹0.00 ₹0.00
CARRIAGE :
Poling boards = 5.7 cum
Ballies 10x40x1.5x3.14/4x0.125² = 7.4 cum.
Total for carriage = 13.1 cum x ¼ = 3.275 cum
LABOUR
0112 Carpenter 2nd class day 5 ₹816.00 ₹4,080.00
0114 Beldar day 8.8 ₹736.00 ₹6,476.80
9999 Sundries L.S. 475.8 ₹2.27 ₹1,080.07

Rate build-up

TOTAL ₹22,549.37
Add 1 % Water charges on "W" ₹225.49
TOTAL ₹22,774.86
Add GST on "X" (multiplying factor 0.2127) ₹4,844.21
TOTAL ₹27,619.07
Add 15% CPOH on "Y" ₹4,142.86
TOTAL ₹31,761.93
Add Cess @ 1% on "Z" ₹317.62
Cost of 450 sqm. ₹32,079.55
Cost per sqm. ₹71.29
Say ₹71.30