DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.14.3.2 rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (blasting prohibited) Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Published rate₹1,778.15DSR 2023
Rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (blasting prohibited)

DSR rate₹1,778.15as per item analysis

Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Item code
2.14.3.2
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
581

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 300m length of a pipe of an average dia. say 450mm.
Slope assumed 1 in 200.
Excavation-
100x1.05x1.75 = 183.75 cum.
200x1.05x(2.00 +3.00)/2= 525.00 cum.
Total = 708.75 cum.
2.9.3 Rate as per item no. 2.9.3 of SH: Earth Work cum 708.75 ₹1,523.05 ₹10,79,461.69
Refilling, ramming and watering = 708.35 cum
2.25 Rate as per item No.2.25 of SH: Earth Work cum 708.75 ₹196.00 ₹1,38,915.00
Extra labour for ramming of rock=(2.75 * 708.85/93.60 = 20.82)(Based on Item No 2.13.3.2)
0114 Beldar day 20.82 ₹736.00 ₹15,323.52
2.13.3.3 Less for depth upto 1.50 m Rate as per Item No.2.13.3.3 of SH: Earth Work metre -300 ₹2,355.75 -₹7,06,725.00
Extra cost for one metre length ₹1,778.17

Rate build-up

TOTAL ₹5,26,975.21
Add 1 % Water charges on "W-A" ₹153.24
TOTAL ₹5,27,128.45
Add GST on "X-A" (multiplying factor 0.2127) ₹3,291.91
TOTAL ₹5,30,420.36
Add 15% CPOH on "Y-A" ₹2,815.30
TOTAL ₹5,33,235.66
Add Cess @ 1% on "Z-A" ₹215.84
Cost for 300m length of pipe ₹5,33,451.50
Say ₹1,778.15

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook