Rate analysis
Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (blasting prohibited)
DSR rate₹1,778.15as per item analysis
Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia
- Item code
- 2.14.3.2
- Sub-head
- SH 2 · EARTH WORK
- Unit
- See analysis
- Source row
- 581
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 300m length of a pipe of an average dia. say 450mm. | |||||
| Slope assumed 1 in 200. | |||||
| Excavation- | |||||
| 100x1.05x1.75 = 183.75 cum. | |||||
| 200x1.05x(2.00 +3.00)/2= 525.00 cum. | |||||
| Total = 708.75 cum. | |||||
| 2.9.3 | Rate as per item no. 2.9.3 of SH: Earth Work | cum | 708.75 | ₹1,523.05 | ₹10,79,461.69 |
| Refilling, ramming and watering = 708.35 cum | |||||
| 2.25 | Rate as per item No.2.25 of SH: Earth Work | cum | 708.75 | ₹196.00 | ₹1,38,915.00 |
| Extra labour for ramming of rock=(2.75 * 708.85/93.60 = 20.82)(Based on Item No 2.13.3.2) | |||||
| 0114 | Beldar | day | 20.82 | ₹736.00 | ₹15,323.52 |
| 2.13.3.3 | Less for depth upto 1.50 m Rate as per Item No.2.13.3.3 of SH: Earth Work | metre | -300 | ₹2,355.75 | -₹7,06,725.00 |
| — | Extra cost for one metre length | — | — | — | ₹1,778.17 |
Rate build-up
| TOTAL | ₹5,26,975.21 |
| Add 1 % Water charges on "W-A" | ₹153.24 |
| TOTAL | ₹5,27,128.45 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹3,291.91 |
| TOTAL | ₹5,30,420.36 |
| Add 15% CPOH on "Y-A" | ₹2,815.30 |
| TOTAL | ₹5,33,235.66 |
| Add Cess @ 1% on "Z-A" | ₹215.84 |
| Cost for 300m length of pipe | ₹5,33,451.50 |
| Say | ₹1,778.15 |