Rate analysis
Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (blasting prohibited)
DSR rate₹826.80as per item analysis
Pipes, cables etc. not exceeding 80 mm dia
- Item code
- 2.13.3.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- See analysis
- Source row
- 358
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 180 m length of a pipe of a average dia. say 40mm. | |||||
| Slope assumed 1:200 | |||||
| Excavation- | |||||
| Quantity same as in item No.2.10.1.1 | |||||
| 2.9.3 | Rate of item no 2.9.3 of SH: Earth Work | cum | 85.05 | ₹1,523.05 | ₹1,29,535.40 |
| Refilling, ramming and watering | |||||
| 2.25 | Rate as per item No.2.25 of SH: Earth Work | cum | 85.05 | ₹196.00 | ₹16,669.80 |
| Extra labour for ramming of rock | |||||
| 0114 | Beldar | day | 2.5 | ₹736.00 | ₹1,840.00 |
Rate build-up
| TOTAL | ₹1,48,045.20 |
| Add 1 % Water charges on "W-A" | ₹18.40 |
| TOTAL | ₹1,48,063.60 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹395.28 |
| TOTAL | ₹1,48,458.88 |
| Add 15% CPOH on "Y-A" | ₹338.05 |
| TOTAL | ₹1,48,796.93 |
| Add Cess @ 1% on "Z-A" | ₹25.92 |
| Cost for 180 m. length of pipe | ₹1,48,822.85 |
| Cost for 1m. length of pipe | ₹826.79 |
| Say | ₹826.80 |