DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.35.3 rate analysis

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 900 mm dia RCC pipes.

Published rate₹5,377.25DSR 2023
Rate analysis

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

DSR rate₹5,377.25as per item analysis

900 mm dia RCC pipes.

Item code
19.35.3
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3584

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail for 10 metre
MATERIALS :
1730 RCC pipe 900 mm dia NP-3 spigot metre 10 ₹3,395.00 ₹33,950.00
2331 Carriage of R.C.C. pipes 900 mm dia 100 metre 0.1 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.025 ₹5,156.00 ₹128.90
2209 Carriage of Cement tonne 0.025 ₹0.00 ₹0.00
0983 Fine sand (zone IV) cum 0.033 ₹980.00 ₹32.34
2261 Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 0.033 ₹0.00 ₹0.00
LABOUR
0123 Mason 1st class day 0.625 ₹897.00 ₹560.63
0124 Mason 2nd class day 0.625 ₹816.00 ₹510.00
0114 Beldar day 3 ₹736.00 ₹2,208.00
0101 Bhisti day 0.5 ₹816.00 ₹408.00
Detail of cost for 10 metre ₹53,772.63
Rate per metre ₹5,377.26

Rate build-up

TOTAL ₹37,797.87
Add 1 % Water charges on "W" ₹377.98
TOTAL ₹38,175.85
Add GST on "X" (multiplying factor 0.2127) ₹8,120.00
TOTAL ₹46,295.85
Add 15% CPOH on "Y" ₹6,944.38
TOTAL ₹53,240.23
Add Cess @ 1% on "Z" ₹532.40
Say ₹5,377.25

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook