DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.35.2 rate analysis

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 600 mm dia RCC pipes.

Published rate₹3,401.25DSR 2023
Rate analysis

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

DSR rate₹3,401.25as per item analysis

600 mm dia RCC pipes.

Item code
19.35.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3584

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail for 10 metre
MATERIALS :
1729 RCC pipe 600 mm dia NP-3 spigot metre 10 ₹2,140.00 ₹21,400.00
2303 Carriage of R.C.C. pipes 600, 700, 750 & 800 mm dia 100 metre 0.1 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.016 ₹5,156.00 ₹82.50
2209 Carriage of Cement tonne 0.016 ₹0.00 ₹0.00
0983 Fine sand (zone IV) cum 0.022 ₹980.00 ₹21.56
2261 Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 0.022 ₹0.00 ₹0.00
LABOUR
0123 Mason 1st class day 0.46 ₹897.00 ₹412.62
0124 Mason 2nd class day 0.46 ₹816.00 ₹375.36
0114 Beldar day 1.83 ₹736.00 ₹1,346.88
0101 Bhisti day 0.33 ₹816.00 ₹269.28
Detail of cost for 10 metre ₹34,012.68
Rate per metre ₹3,401.27

Rate build-up

TOTAL ₹23,908.20
Add 1 % Water charges on "W" ₹239.08
TOTAL ₹24,147.28
Add GST on "X" (multiplying factor 0.2127) ₹5,136.13
TOTAL ₹29,283.41
Add 15% CPOH on "Y" ₹4,392.51
TOTAL ₹33,675.92
Add Cess @ 1% on "Z" ₹336.76
Say ₹3,401.25