DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.33 rate analysis

Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design.

Published rate₹2,890.10DSR 2023
Rate analysis

Constructing soak pit 1.20x1.20x1.20 m filled with brickbats including S.W. drain pipe 100 mm diameter and 1.20 m long complete as per standard design.

DSR rate₹2,890.10as per item analysis
Item code
19.33
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3499

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one soak pit
Earth work in excavation including disposal of surplus earth 1.2x1.2x1.2m = 1.73 cum
2.8.1 (Rate as per item no. 2.8.1 of SH: Earth work) cum 1.73 ₹260.30 ₹450.32
0362 Brick bats cum 1.73 ₹525.00 ₹908.25
1.2x1.2x1.2 = 1.73 cum
2260 Carriage of Brick aggregate cum 1.73 ₹0.00 ₹0.00
16.8.1 Rate as per item no. 16.8.1 of SH : Road work metre 5.2 ₹53.45 ₹277.94
Second class brick edging laid length wise with half brick depth
1854 Stoneware pipes grade A (60 cm long) 100 mm dia each 2 ₹77.00 ₹154.00
9999 Sundries L.S. 25.84 ₹2.27 ₹58.66
LABOUR
For filling brick bats
0114 Beldar day 0.5 ₹736.00 ₹368.00
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹2,247.86
Add 1 % Water charges on "W-A" ₹15.20
TOTAL ₹2,263.06
Add GST on "X-A" (multiplying factor 0.2127) ₹326.45
TOTAL ₹2,589.51
Add 15% CPOH on "Y-A" ₹279.19
TOTAL ₹2,868.70
Add Cess @ 1% on "Z-A" ₹21.40
Cost of one soak pit ₹2,890.10
Say ₹2,890.10