Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per standard design. With common burnt clay F.P.S. (non modular) bricks of class designation 7.5

Published rate₹26,861.90DSR 2023
Rate analysis

Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per standard design.

DSR rate₹26,861.90as per item analysis

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5

Item code
19.32.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3446

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one soak pit
Earth work in excavation including disposal of surplus earth 3.14/4x(2.5)²x3m = 14.73 cum
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 14.73 ₹260.30 ₹3,834.22
= 3.14/4x(2.5)² x 1.5 m = 7.37 cum
2nd class bricks
perimetre = 4x0.35 =1.40 m
Area = 1.40x2.925 m = 4.1 sqm
Number of brick = 4.1x487x0.066 = 131.78
Wastage 10% = 13.718
Total= 144.96 Say 145 numbers
2602 Common burnt clay F.P.S. (non modular) bricks class designation 7.5 1000 Nos 0.145 ₹4,724.00 ₹684.98
Brick bats = 3.14/4x(1.2)²x2.925m =3.33 cum
Deduct = 0.45x0.45x2.925 m = 0.59 cum
Net qty= 2.74 cum
0362 Brick bats cum 2.74 ₹525.00 ₹1,438.50
Brick aggregate 50 to 80 mm nominal size = 3.14x1.50x0.03x2.925 m = 4.13 cum
0285 Brick Aggregate (Single size) : 63 mm nominal size cum 4.13 ₹700.00 ₹2,891.00
Brick aggregate 40 mm nominal size
= 3.14x2.15x0.35x2.925 m =6.91 cum
0287 Brick Aggregate (Single size) : 40 mm nominal size cum 6.91 ₹700.00 ₹4,837.00
1854 Stoneware pipes grade A (60 cm long) 100 mm dia each 3 ₹77.00 ₹231.00
Carriage of brick bats and aggregate
2260 Carriage of Brick aggregate cum 13.78 ₹0.00 ₹0.00
2201 Carriage of Bricks 1000 Nos 0.145 ₹0.00 ₹0.00
9999 Single matting 2.5x2.5 m = 6.25 sqm L.S. 112.14 ₹2.27 ₹254.56
Precast R.C.C.slabs 7.5 cm thick in
cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
0.45x0.45x0.075 m = 0.02 cum
5.12 Rate as per item no 5.12 of SH : RCC cum 0.02 ₹10,585.90 ₹211.72
Reinforcement @ 80 kg/cum = 0.02x80 =1.6 kg
5.22.6 Rate as per item no. 5.22.6 of SH : RCC work kg 1.6 ₹107.85 ₹172.56
2nd class brick edging laid length wise with half brick depth
3.14x2.6 m =8.17 m
16.8.1 Rate as per item no. 16.8.1 of SH : Road work metre 8.17 ₹53.45 ₹436.69
LABOUR
0123 Mason 1st class day 0.5 ₹897.00 ₹448.50
0124 Mason 2nd class day 0.5 ₹816.00 ₹408.00
0114 Beldar day 3 ₹736.00 ₹2,208.00
0115 Coolie day 3 ₹736.00 ₹2,208.00

Rate build-up

TOTAL ₹20,264.73
Add 1 % Water charges on "W-A" ₹156.10
TOTAL ₹20,420.83
Add GST on "X-A" (multiplying factor 0.2127) ₹3,353.35
TOTAL ₹23,774.18
Add 15% CPOH on "Y-A" ₹2,867.85
TOTAL ₹26,642.03
Add Cess @ 1% on "Z-A" ₹219.87
Cost of one soak pit ₹26,861.90
Say ₹26,861.90