DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.26.4 rate analysis

Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately) : Circular manhole 140 cm dia with circular cover 600 mm dia of grade EHD - 35

Published rate₹320.15DSR 2023
Rate analysis

Raising manhole cover and frame slab to required level including dismantling existing slab and making good the damage as required (Raising depth of manhole to be paid separately) :

DSR rate₹320.15as per item analysis

Circular manhole 140 cm dia with circular cover 600 mm dia of grade EHD - 35

Item code
19.26.4
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2991

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one manhole
Dismantling of C.C slab of 1:2:4 (1 cement 2 coarse sand : 4 aggregate stone 20 mm nominal size)
= 3.14/4x(0.985)²x0.15 = 0.114 cum
Less cover =3.14/4x(0.90)²x0.15 =(-) 0.095 cum
Net qty= 0.019 cum Say 0.02 cum
15.3 Rate as per item no. 15.3 of SH : Dismantling and demolishing cum 0.02 ₹3,551.25 ₹71.03
9999 Removal of R.C.C cover and frame L.S. 8.06 ₹2.27 ₹18.30
C.C work 1:2:4 ( 1 cement : 2 coarse sand 4 graded stone aggregate 20 mm nominal size )
3.14/4x(0.985)²x0.15 = 0.114 cum
Less portion cover with frame = 3.14/4x(0.90)²x0.15 =(-) 0.095 cum
Net qty= 0.019 cum Say 0.02 cum
4.1.3 Rate as per item no 4.1.3 of SH : Concrete Work cum 0.02 ₹7,878.50 ₹157.57
9999 Sundries L.S. 20.28 ₹2.27 ₹46.04

Rate build-up

TOTAL ₹292.94
Add 1 % Water charges on "W-A" ₹0.64
TOTAL ₹293.58
Add GST on "X-A" (multiplying factor 0.2127) ₹13.82
TOTAL ₹307.40
Add 15% CPOH on "Y-A" ₹11.82
TOTAL ₹319.22
Add Cess @ 1% on "Z-A" ₹0.91
Cost of one no ₹320.13
Say ₹320.15