DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.22.1 rate analysis

Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe and bend encased all-round with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) with all centering and shuttering required, cutting holes in walls and making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall, lead caulked joints between sand cast iron pipes and fittings, stiff cement mortar 1:1 (1 cement : 1 fine sand) joints between sand cast iron tee and S.W. pipe, making required channels complete as per standard design and specifications : 100 mm dia sand cast iron drop connection

Published rate₹12,172.05DSR 2023
Rate analysis

Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe and bend encased all-round with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) with all centering and shuttering required, cutting holes in walls and making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall, lead caulked joints between sand cast iron pipes and fittings, stiff cement mortar 1:1 (1 cement : 1 fine sand) joints between sand cast iron tee and S.W. pipe, making required channels complete as per standard design and specifications :

DSR rate₹12,172.05as per item analysis

100 mm dia sand cast iron drop connection

Item code
19.22.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2511

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one drop connection
MATERIAL
1617 S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 100mm dia each 0.556 ₹1,200.00 ₹667.20
= 37+30+33 =101 cm =1.00 m
Length of pipe = 1.00 m. Hence, Qty = 1.00 /1.8 =0.556 Nos
9977 Carriage of pipe L.S. 1.43 ₹2.27 ₹3.25
Cutting charges
18.83.2 Rate as per item no 18.83.2 of SH: Water supply each cut 3 ₹194.70 ₹584.10
1336 Clearing eye with chain and lid 100 mm dia each 1 ₹50.00 ₹50.00
1621 S.C.I. plain bend 100 mm dia each 1 ₹300.00 ₹300.00
1628 S.C.I. plain single equal junctions 100x100x100 mm dia each 1 ₹410.00 ₹410.00
Brick work in cement mortar 1:4 (1 cement : 4 coarse sand)
0.20x0.20x0.23 = 0.009 cum
Less pipe 1/2x3.14x0.10x0.10x0.23 = 0.002 cum
Net Qty= 0.009 - 0.002 = 0.007 cum
6.1.1 Rate as per item no 6.1.1 of SH : Brick Work cum 0.007 ₹7,370.65 ₹51.59
Cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size)
0.40x0.45x1.05 m = 0.189 cum
0.40x0.25x0.40 = 0.040 cum
Total= 0.229 cum
Less pipe portion
1/2x3.14x0.10x0.10x1.50 = 0.012 cum
Toothing portion
2x0.40x0.05x0.10 m = 0.004 cum = 0.016 cum
Net Qty= 0.229-0.016 = 0.213 cum Say 0.21 cum
4.1.11 Rate as per item no 4.1.11 of SH : Concrete Work cum 0.21 ₹6,189.65 ₹1,299.83
12 mm cement plaster 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement
1x0.25x0.25 m = 0.0625 Say 0.06 sqm
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 0.06 ₹449.55 ₹26.97
Providing lead caulked joints to 100 mm diameter pipe and special
12.39.1 Rate as per item no. 12.39.1 of SH : Roofing each 4 ₹580.50 ₹2,322.00
9999 Providing joint to S.W. pipe with cement mortar 1:1 (1 cement : 1 fine sand) L.S. 26.91 ₹2.27 ₹61.09
Form work
1.30x1.05 m = 1.36 sqm
5.9.2 Rate as per item no 5.9.2 of SH : RCC sqm 1.36 ₹842.50 ₹1,145.80
9988 Sundries including carriage of bends etc. L.S. 26.91 ₹2.27 ₹61.09
LABOUR
For cutting holes 5 cm deep in alternate course of brick work benching and channel
0123 Mason 1st class day 0.7 ₹897.00 ₹627.90
0124 Mason 2nd class day 0.7 ₹816.00 ₹571.20
0114 Beldar day 2.7 ₹736.00 ₹1,987.20

Rate build-up

TOTAL ₹10,169.22
Add 1 % Water charges on "W-A" ₹47.39
TOTAL ₹10,216.61
Add GST on "X-A" (multiplying factor 0.2127) ₹1,018.05
TOTAL ₹11,234.66
Add 15% CPOH on "Y-A" ₹870.66
TOTAL ₹12,105.32
Add Cess @ 1% on "Z-A" ₹66.75
Cost of one drop connection ₹12,172.07
Say ₹12,172.05