DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.21.3 rate analysis

Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : For pipes 350 to 450 mm diameter

Published rate₹1,328.45DSR 2023
Rate analysis

Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete :

DSR rate₹1,328.45as per item analysis

For pipes 350 to 450 mm diameter

Item code
19.21.3
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2423

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one connection
MATERIAL
Cement concrete 1:2:4 mix ( 1 cement : 2 coarse sand : 4 grade stone aggregate 20 mm nominal size )
= 0.50x0.50x0.30 m = 0.075 cum
Less pipe = 1/2x3.14x0.45x0.45x0.30 = 0.048 cum
= 0.027 cum Say 0.03 cum
4.1.3 Rate as per item no. 4.1.3 of SH : Concrete Work cum 0.03 ₹7,878.50 ₹236.36
12 mm cement plater 1:3 ( 1 cement : 3 coarse sand ) finished with a floating coat of neat cement
2x0.55x0.55 =0.605 sqm Say 0.60 sqm
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 0.6 ₹449.55 ₹269.73
LABOUR
(For cutting holes average size 30x30 cm in 23 cm thick wall and making channel etc.)
0123 Mason 1st class day 0.16 ₹897.00 ₹143.52
0124 Mason 2nd class day 0.16 ₹816.00 ₹130.56
0114 Beldar day 0.33 ₹736.00 ₹242.88
9999 Add for delay sundries etc. L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹1,084.14
Add 1 % Water charges on "W-A" ₹5.78
TOTAL ₹1,089.92
Add GST on "X-A" (multiplying factor 0.2127) ₹124.18
TOTAL ₹1,214.10
Add 15% CPOH on "Y-A" ₹106.20
TOTAL ₹1,320.30
Add Cess @ 1% on "Z-A" ₹8.14
Cost for 1 connection ₹1,328.44
Say ₹1,328.45