DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.2.2 rate analysis

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design : 150 mm diameter S.W. pipe

Published rate₹1,179.85DSR 2023
Rate analysis

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design :

DSR rate₹1,179.85as per item analysis

150 mm diameter S.W. pipe

Item code
19.2.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
167

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metre
Area = W x W/2 + ½ x (3.14 x W² / 4)- (3.14 x D² / 4)
= W² x (0.5 + 3.14 / 8) - (3.14 x D² / 4)
Where W = D + X
D = 150 + 16 + 16 = 182 mm or 18.2 cm
X = 300 mm as trench depth is less than 1200 mm
W = 18.2 + 30 = 48.2
Area = 48.2² x ( 0.5 + 3.14/ 8) - (3.14 x 18.2 ²/4)
= 1807.66 sqcm = 0.1808 sqm. Say 0.181 sqm
For 10 m length qty. of concrete reqd. = 1.81 cum
4.1.10 Rate as per item no 4.1.10 of SH : Concrete Work cum 1.81 ₹6,518.60 ₹11,798.67

Rate build-up

Cost of 10 metres ₹11,798.67
Cost of metre ₹1,179.87
Say ₹1,179.85

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook