DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.2.1 rate analysis

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design : 100 mm diameter S.W. pipe

Published rate₹964.75DSR 2023
Rate analysis

Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) all-round S.W. pipes including bed concrete as per standard design :

DSR rate₹964.75as per item analysis

100 mm diameter S.W. pipe

Item code
19.2.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
167

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metre
Area = W x W/2 + ½ x (3.14 x W² / 4) - (3.14 x D² / 4)
= W² x (0.5 + 3.14 / 8) - (3.14 x D² / 4)
Where W = D + X
D = 100 + 12 + 12 = 124 mm or 12.4 cm
X = 300 mm as trench depth is less than 1200 mm
W = 12.4 + 30 = 42.4
Area= 42.4² x ( 0.5 + 3.14/ 8) - (3.14 x 12.4²/4)
= 1484 sqcm = 0.1484 sqm Say 0.148 sqm
For 10 m length qty. of concrete reqd. = 1.48 cum
4.1.10 Rate as per item no 4.1.10 of SH : Concrete Work cum 1.48 ₹6,518.60 ₹9,647.53

Rate build-up

Cost of 10 metres ₹9,647.53
Cost of metre ₹964.75
Say ₹964.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook