DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.36.1 rate analysis

Constructing masonry Chamber 60x60x75 cm, inside in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for fire hydrants, with C.I. surface box 350x350 mm top and 165 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ) , i/c necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Published rate₹10,354.95DSR 2023
Rate analysis

Constructing masonry Chamber 60x60x75 cm, inside in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for fire hydrants, with C.I. surface box 350x350 mm top and 165 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ) , i/c necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design :

DSR rate₹10,354.95as per item analysis

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Item code
18.36.1
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
4023

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one chamber
MATERIAL
(i) Earth work in excavation including refilling and disposal of surplus earth
1.21X1.21X1.00m = 1.464cum. Say 1.46cum.
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 1.46 ₹260.30 ₹380.04
2.25 Rate as per item No.2.25 of SH: Earth work cum 1.46 ₹196.00 ₹286.16
(ii) Cement concrete 1:5:10 (1 Cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size)
1.21x1.21x0.1m=0.146cum. Say 0.15 cum.
4.1.11 Rate as per item no 4.1.11 of SH : Concrete Work cum 0.15 ₹6,189.65 ₹928.45
(iii) Second class brick work in cement mortar 1:4 (1 Cement : 4 coarse sand) in foundations and plinth
3.32mx0.23mx0.75m=0.573cum.
6.1.1 Rate as per item no 6.1.1 of SH : Brick Work cum 0.57 ₹7,370.65 ₹4,201.27
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse sand) finished with a floating coat of neat cement.
2.40mx0.75m=1.80sqm.
0.90mx0.90m =0.36sqm.
Total=2.16sqm.
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 2.16 ₹449.55 ₹971.03
(v) C.I. surface box with chained lid
1305 Surface box for sluice valve each 1 ₹200.00 ₹200.00
9977 (vi) Carriage of C.I. surface box L.S. 53.82 ₹2.27 ₹122.17
(vii) Cement concrete 1:1.5:3 (1 Cement : 1.5 Coarse sand : 3 graded stone aggregate 20mm nominal size)
in slab = 1.06mx1.06mx0.15m = 0.1685 cum.
Less surface box 0.61x0.41mx0.15m=
(-)0.0375 cum.
= 0.131 cum. Say 0.13 cum.
5.1.2 Rate as per item no. 5.1.2 of SH : RCC work cum 0.13 ₹9,045.75 ₹1,175.95
(viii)T.M.T. bars steel reinforcement for R.C.C work
0.131cumx80kg/cum. = 10.48kg.
5.22.6 Rate as per item no. 5.22.6 of SH : RCC work kg 10.48 ₹107.85 ₹1,130.27
(ix) Form work
0.60mx0.60m=0.36sqm.+
3.32mx0.15m = 0.50 sqm.
Total =0.86 sqm.
5.9.3 Rate as per item No.5.9.3 Of SH: RCC sqm 0.86 ₹927.25 ₹797.44
(x)
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

Say 0.57 cum.
TOTAL ₹10,211.08
Add 1 % Water charges on "W-A" ₹3.40
TOTAL ₹10,214.48
Add GST on "X-A" (multiplying factor 0.2127) ₹73.14
TOTAL ₹10,287.62
Add 15% CPOH on "Y-A" ₹62.55
TOTAL ₹10,350.17
Add Cess @ 1% on "Z-A" ₹4.80
Cost of one manhole ₹10,354.97
Say ₹10,354.95