DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.35.1 rate analysis

Constructing masonry Chamber 120x120x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), i/c necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Published rate₹26,163.40DSR 2023
Rate analysis

Constructing masonry Chamber 120x120x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), i/c necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design :

DSR rate₹26,163.40as per item analysis

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Item code
18.35.1
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
3972

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one chamber
MATERIAL
(i) Earth work in excavation including refilling and disposal of surplus earth
1.81X1.81X1.25M
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 4.1 ₹260.30 ₹1,067.23
2.25 Rate as per item No.2.25 of SH: Earth work cum 4.1 ₹196.00 ₹803.60
(ii) Cement concrete 1:5:10 (1 Cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size)
1.81x1.81x0.1m=0.328cum. Say 0.33 cum.
4.1.11 Rate as per item no 4.1.11 of SH : Concrete Work cum 0.33 ₹6,189.65 ₹2,042.58
(iii) Second class brick work in cement mortar 1:4 (1 Cement : 4coarse sand) in foundations and plinth
5.72mx0.23mx1.00m=1.316cum.
6.1.1 Rate as per item no 6.1.1 of SH : Brick Work cum 1.32 ₹7,370.65 ₹9,729.26
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse sand) finished with a floating coat of neat cement.
4.80mx1.00m=4.80sqm.
1.20mx1.20m=1.44sqm.
Total=6.24sqm.
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 6.24 ₹449.55 ₹2,805.19
(v) C.I. surface box with chained lid
1305 Surface box for sluice valve each 1 ₹200.00 ₹200.00
9977 (vi) Carriage of C.I. surface box L.S. 8.06 ₹2.27 ₹18.30
(vii) Cement concrete 1:1.5:3 (1 Cement : 1.5 Coarse sand : 3 graded stone aggregate 20mm nominal size)
in slab = 1.66mx1.66mx0.15m = 0.4133 cum.
Less surface box 0.7854x0.156mx
0.156mx0.18m = (-)0.0034 cum.
Total= 0.4099 cum. Say 0.41 cum.
5.1.2 Rate as per item no. 5.1.2 of SH : RCC work cum 0.41 ₹9,045.75 ₹3,708.76
(viii)T.M.T. bars steel reinforcement for R.C.C work
0.41cum.x80kg/cum. = 32.80kg.
5.22.6 Rate as per item no. 5.22.6 of SH : RCC work kg 32.8 ₹107.85 ₹3,537.48
(ix) Form work
1.20mx1.20m=1.44sqm.+
5.72mx0.15m=0.86 sqm.
Total = 2.30sqm.
5.9.3 Rate as per item No.5.9.3 Of SH: RCC sqm 2.3 ₹927.25 ₹2,132.68
(x)
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

Say 1.32 cum.
TOTAL ₹26,063.38
Add 1 % Water charges on "W-A" ₹2.37
TOTAL ₹26,065.75
Add GST on "X-A" (multiplying factor 0.2127) ₹50.83
TOTAL ₹26,116.58
Add 15% CPOH on "Y-A" ₹43.47
TOTAL ₹26,160.05
Add Cess @ 1% on "Z-A" ₹3.33
Cost of one manhole ₹26,163.38
Say ₹26,163.40

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook