DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.32.1 rate analysis

Constructing masonry Chamber 30x30x50 cm inside, in brick work in cement mortar 1:4 (1 cement :4 coarse sand) for stop cock, with C. I. surface box 100x100 x75 mm (inside) with hinged cover fixed in reinforced cement concrete slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), i/c necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Published rate₹1,992.60DSR 2023
Rate analysis

Constructing masonry Chamber 30x30x50 cm inside, in brick work in cement mortar 1:4 (1 cement :4 coarse sand) for stop cock, with C. I. surface box 100x100 x75 mm (inside) with hinged cover fixed in reinforced cement concrete slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), i/c necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12mm thick, finished with a floating coat of neat cement complete as per standard design :

DSR rate₹1,992.60as per item analysis

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Item code
18.32.1
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
3828

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one chamber
MATERIAL
(i) Earth work in excavation including refilling and disposal of surplus earth
0.68x0.68x0.65m=0.301cum.
2.8.1 (Rate as per item no. 2.8.1 of SH: Earth work) cum 0.3 ₹260.30 ₹78.09
2.25 Rate as per item No.2.25 cum 0.3 ₹196.00 ₹58.80
(ii) Cement concrete 1:5:10 (1 Cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size)
0.68x0.68x0.075m=0.035cum. Say 0.04 cum.
4.1.11 Rate as per item no 4.1.11 of SH : Concrete work cum 0.04 ₹6,189.65 ₹247.59
(iii) Half brick masonry with FPS bricks of class 7.5 in cement mortar 1:4 (1 Cement : 4 coarse sand) in foundations and plinth
1.66mx0.50m=0.83 sqm
6.12.2 Rate as per item no 6.12.2 of SH : Brick Work sqm 0.83 ₹905.05 ₹751.19
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse sand) finished with a floating coat of neat cement.
1.20x0.50=0.60sqm
0.30x0.30=0.09sqm.
Total =0.69sqm. Say 0.70sqm.
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 0.7 ₹449.55 ₹314.69
1304 Surface box for stop cock each 1 ₹120.00 ₹120.00
(vi)
9977 Carriage of C.I. surface box L.S. 1.43 ₹2.27 ₹3.25
(vii) Cement concrete 1:1.5:3 (1 Cement : 1.5 Coarse sand : 3 graded stone aggregate 20mm nominal size) in slab = 0.53mx0.53mx0.075m = 0.02107cum.
Less surface box 0.112x0.112x0.076 =(-)0.00094 cum.
= 0.0201 cum. Say 0.02cum.
5.1.2 Rate as per item no. 5.1.2 of SH : RCC work cum 0.02 ₹9,045.75 ₹180.92
(viii)T.M.T. bars steel reinforcement for R.C.C work
0.02 cumx80kg/cum. = 1.60kg
5.22.6 Rate as per item no. 5.22.6 of SH : RCC work kg 1.6 ₹107.85 ₹172.56
9999 Sundries L.S. 4.16 ₹2.27 ₹9.44

Rate build-up

TOTAL ₹1,936.53
Add 1 % Water charges on "W-A" ₹1.33
TOTAL ₹1,937.86
Add GST on "X-A" (multiplying factor 0.2127) ₹28.51
TOTAL ₹1,966.37
Add 15% CPOH on "Y-A" ₹24.38
TOTAL ₹1,990.75
Add Cess @ 1% on "Z-A" ₹1.87
Cost of one manhole ₹1,992.62
Say ₹1,992.60