DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.77.2 rate analysis

Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of M.S. flat brackets made of 50x5 mm flat of specified shape, projecting 75 mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion hold fasteners, including drilling necessary holes in brick wall/ CC/ RCC surface and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30 mm x1.6 mm galvanised M.S. flats of specified shape and of total length 420 mm and shall be fixed with M.S. nuts, bolts, & washers of size 25x6 mm, one bolts on each side of the pipe. Total bracket length 810 mm of approved shape and design (for two 100 mm dia pipes)

Published rate₹378.10DSR 2023
Rate analysis

Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of M.S. flat brackets made of 50x5 mm flat of specified shape, projecting 75 mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion hold fasteners, including drilling necessary holes in brick wall/ CC/ RCC surface and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30 mm x1.6 mm galvanised M.S. flats of specified shape and of total length 420 mm and shall be fixed with M.S. nuts, bolts, & washers of size 25x6 mm, one bolts on each side of the pipe.

DSR rate₹378.10as per item analysis

Total bracket length 810 mm of approved shape and design (for two 100 mm dia pipes)

Item code
17.77.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
4561

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 50 nos.
MATERIAL
M.S. flats 50x5mm= 50 x 0.81 = 40.5m
@ 1.97 kg/ metre = 79.8 kg.
M.S. flats 30x1.6mm =50x2x0.42 = 42m.
0.38kg/metre = 16kg.
Total = 95.8kg.
Add wastage 5% = 4.8kg.
Total = 100.6 kg.
M.S.flats= 100.6kg. = 1.006 quintal
1007 Structurals such as tees,angles channels and R.S. joists quintal 1.006 ₹5,965.00 ₹6,000.79
2205 Carriage of Steel tonne 0.101 ₹0.00 ₹0.00
LABOUR
0116 Fitter (grade 1) day 0.48 ₹897.00 ₹430.56
0103 Blacksmith 2nd class day 0.72 ₹816.00 ₹587.52
0114 Beldar day 0.96 ₹736.00 ₹706.56
priming coat
50x0.81x0.11 = 4.46
50x2x0.42x0.063 = 2.65
Total =7.11sqm
13.85.1 Rate as per item no 13.85.1 of SH : Finishing sqm 7.11 ₹70.35 ₹500.19
9999 Sundries L.S. 19.8 ₹2.27 ₹44.95
P/F expansion hold fasteners 6mm threaded dia = 50x4 Nos = 200 nos.
8.8.1.1 Rate asper item no. 8.8.1.1 of SH :- Marble work each 200 ₹36.75 ₹7,350.00

Rate build-up

TOTAL ₹15,620.57
Add 1 % Water charges on "W-A" ₹77.70
TOTAL ₹15,698.27
Add GST on "X-A" (multiplying factor 0.2127) ₹1,669.29
TOTAL ₹17,367.56
Add 15% CPOH on "Y-A" ₹1,427.61
TOTAL ₹18,795.17
Add Cess @ 1% on "Z-A" ₹109.45
Cost of 50 Nos. ₹18,904.62
Cost of each ₹378.09
Say ₹378.10