CPWD DSR item 17.5.1 rate analysis

Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350 mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including painting of fittings and cutting and making good the walls and floors wherever required : Single half stall urinal with 5 litre P.V.C. automatic flushing cistern

Published rate₹12,071.75DSR 2023
Rate analysis

Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350 mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including painting of fittings and cutting and making good the walls and floors wherever required :

DSR rate₹12,071.75as per item analysis

Single half stall urinal with 5 litre P.V.C. automatic flushing cistern

Item code
17.5.1
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
268

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
7379 White vitreous china clay half stall urinal flat back 580x380x350 mm or angle back 450x375x350 mm with waste fittings as per IS : 2556 each 1 ₹915.00 ₹915.00
7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 ₹477.00 ₹477.00
1532 Flush pipe with union spreaders and clamps all in C.P. brass for single stall each 1 ₹325.00 ₹325.00
1891 C.I. trap for standard urinal with vent arm with operating and other couplings in C.P.brass: 50 mm dia each 1 ₹209.00 ₹209.00
9999 Red lead, white lead and gaskit L.S. 17.55 ₹2.27 ₹39.84
9999 Cement, sand and grit etc. L.S. 26.91 ₹2.27 ₹61.09
9999 Painting of fittings etc. L.S. 26 ₹2.27 ₹59.02
9977 Carriage of materials L.S. 40.43 ₹2.27 ₹91.78
LABOUR
0116 Fitter (grade 1) day 1.75 ₹897.00 ₹1,569.75
0123 Mason 1st class day 2 ₹897.00 ₹1,794.00
0114 Beldar day 4 ₹736.00 ₹2,944.00

Rate build-up

TOTAL ₹8,485.48
Add 1 % Water charges on "W" ₹84.85
TOTAL ₹8,570.33
Add GST on "X" (multiplying factor 0.2127) ₹1,822.91
TOTAL ₹10,393.24
Add 15% CPOH on "Y" ₹1,558.99
TOTAL ₹11,952.23
Add Cess @ 1% on "Z" ₹119.52
Cost of each ₹12,071.75
Say ₹12,071.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook