Rate analysis
Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes :
DSR rate₹198.15per joint
100 mm dia pipe
- Item code
- 17.36.2
- Sub-head
- SH 17 · SANITARY INSTALLATIONS
- Unit
- joint
- Source row
- 2108
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 4 joints | |||||
| MATERIAL | |||||
| 9999 | Cement mortar, spun yarn etc. | L.S. | 8.06 | ₹2.27 | ₹18.30 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 0.33 | ₹897.00 | ₹296.01 |
| 0114 | Beldar | day | 0.33 | ₹736.00 | ₹242.88 |
Rate build-up
| TOTAL | ₹557.19 |
| Add 1 % Water charges on "W" | ₹5.57 |
| TOTAL | ₹562.76 |
| Add GST on "X" (multiplying factor 0.2127) | ₹119.70 |
| TOTAL | ₹682.46 |
| Add 15% CPOH on "Y" | ₹102.37 |
| TOTAL | ₹784.83 |
| Add Cess @ 1% on "Z" | ₹7.85 |
| Cost of 4 joints | ₹792.68 |
| Cost of 1 joint | ₹198.17 |
| Say | ₹198.15 |