DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.36.2 rate analysis

Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 100 mm dia pipe

Published rate₹198.15per joint
Rate analysis

Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes :

DSR rate₹198.15per joint

100 mm dia pipe

Item code
17.36.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
joint
Source row
2108

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 4 joints
MATERIAL
9999 Cement mortar, spun yarn etc. L.S. 8.06 ₹2.27 ₹18.30
LABOUR
0116 Fitter (grade 1) day 0.33 ₹897.00 ₹296.01
0114 Beldar day 0.33 ₹736.00 ₹242.88

Rate build-up

TOTAL ₹557.19
Add 1 % Water charges on "W" ₹5.57
TOTAL ₹562.76
Add GST on "X" (multiplying factor 0.2127) ₹119.70
TOTAL ₹682.46
Add 15% CPOH on "Y" ₹102.37
TOTAL ₹784.83
Add Cess @ 1% on "Z" ₹7.85
Cost of 4 joints ₹792.68
Cost of 1 joint ₹198.17
Say ₹198.15