Rate analysis
Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes :
DSR rate₹168.20per joint
75 mm dia pipe
- Item code
- 17.36.1
- Sub-head
- SH 17 · SANITARY INSTALLATIONS
- Unit
- joint
- Source row
- 2108
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 4 joints | |||||
| MATERIAL | |||||
| 9999 | Cement mortar, spun yarn etc. | L.S. | 6.89 | ₹2.27 | ₹15.64 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 0.28 | ₹897.00 | ₹251.16 |
| 0114 | Beldar | day | 0.28 | ₹736.00 | ₹206.08 |
Rate build-up
| TOTAL | ₹472.88 |
| Add 1 % Water charges on "W" | ₹4.73 |
| TOTAL | ₹477.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹101.59 |
| TOTAL | ₹579.20 |
| Add 15% CPOH on "Y" | ₹86.88 |
| TOTAL | ₹666.08 |
| Add Cess @ 1% on "Z" | ₹6.66 |
| Cost of 4 joints | ₹672.74 |
| Cost of 1 joint | ₹168.19 |
| Say | ₹168.20 |