DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.36.1 rate analysis

Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 75 mm dia pipe

Published rate₹168.20per joint
Rate analysis

Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./ C.I. Pipes :

DSR rate₹168.20per joint

75 mm dia pipe

Item code
17.36.1
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
joint
Source row
2108

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 4 joints
MATERIAL
9999 Cement mortar, spun yarn etc. L.S. 6.89 ₹2.27 ₹15.64
LABOUR
0116 Fitter (grade 1) day 0.28 ₹897.00 ₹251.16
0114 Beldar day 0.28 ₹736.00 ₹206.08

Rate build-up

TOTAL ₹472.88
Add 1 % Water charges on "W" ₹4.73
TOTAL ₹477.61
Add GST on "X" (multiplying factor 0.2127) ₹101.59
TOTAL ₹579.20
Add 15% CPOH on "Y" ₹86.88
TOTAL ₹666.08
Add Cess @ 1% on "Z" ₹6.66
Cost of 4 joints ₹672.74
Cost of 1 joint ₹168.19
Say ₹168.20