Rate analysis
75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with :
DSR rate₹76.30per sqm
Moorum
- Item code
- 16.74.1
- Sub-head
- SH 16 · ROAD WORK
- Unit
- sqm
- Source row
- 4647
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 sqm | |||||
| MATERIAL | |||||
| 0810 | Moorum | cum | 7.5 | ₹540.00 | ₹4,050.00 |
| Carriage by mechanical transport i/c loading unloading and stacking | |||||
| 2265 | Carriage of Moorum | cum | 7.5 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0114 | Beldar | day | 1.64 | ₹736.00 | ₹1,207.04 |
| 0101 | Bhisti | day | 0.13 | ₹816.00 | ₹106.08 |
Rate build-up
| TOTAL | ₹5,363.12 |
| Add 1 % Water charges on "W" | ₹53.63 |
| TOTAL | ₹5,416.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,152.14 |
| TOTAL | ₹6,568.89 |
| Add 15% CPOH on "Y" | ₹985.33 |
| TOTAL | ₹7,554.22 |
| Add Cess @ 1% on "Z" | ₹75.54 |
| Cost for 100 sqm | ₹7,629.76 |
| Cost per sqm | ₹76.30 |