Rate analysis
Made of G.I. wire of dia. 4 mm, PVC coated to achieve outer dia not less than 5 mm in required colour and shade
DSR rate₹1,067.10as per item analysis
- Item code
- 16.70.2
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 4556
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm. | |||||
| MATERIAL | |||||
| G.I. chain link 50x50 mm mesh PVC coated = 10.00 sqm. | |||||
| Wastage @ 5% = 0.50 sqm. | |||||
| Total = 10.50 sqm. | |||||
| 8696 | Chain link fabric fencing mesh of size 50x50 mm made of G.I. wire of dia 4 mm, PVC coated to outer dia 5 mm | sqm | 10.5 | ₹363.00 | ₹3,811.50 |
| 9977 | Carriage. | L.S. | 156 | ₹2.27 | ₹354.12 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 2.14 | ₹816.00 | ₹1,746.24 |
| 0114 | Beldar | day | 1.62 | ₹736.00 | ₹1,192.32 |
| 9999 | Sundries including G.I. wire, nuts and bolts and warshers. | L.S. | 174.75 | ₹2.27 | ₹396.68 |
Rate build-up
| TOTAL | ₹7,500.86 |
| Add 1 % Water charges on "W" | ₹75.01 |
| TOTAL | ₹7,575.87 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,611.39 |
| TOTAL | ₹9,187.26 |
| Add 15% CPOH on "Y" | ₹1,378.09 |
| TOTAL | ₹10,565.35 |
| Add Cess @ 1% on "Z" | ₹105.65 |
| Cost for 10 sqm. | ₹10,671.00 |
| Cost for 1 sqm. | ₹1,067.10 |
| Say | ₹1,067.10 |