CPWD DSR item 16.70.1 rate analysis

Made of G.I. wire of dia 4 mm

Published rate₹1,017.80DSR 2023
Rate analysis

Made of G.I. wire of dia 4 mm

DSR rate₹1,017.80as per item analysis
Item code
16.70.1
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
4531

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm.
MATERIAL
G.I. chain link 50x50 mm mesh = 10.00 sqm.
Wastage @ 5% = 0.50 sqm.
Total = 10.50 sqm.
8695 Chain link fabric fencing mesh of size 50x50 mm made of G.I. wire of dia 4 mm sqm 10.5 ₹330.00 ₹3,465.00
9977 Carriage. L.S. 156 ₹2.27 ₹354.12
LABOUR
0103 Blacksmith 2nd class day 2.14 ₹816.00 ₹1,746.24
0114 Beldar day 1.62 ₹736.00 ₹1,192.32
9999 Sundries including G.I. wire, nuts and bolts and warshers. L.S. 174.75 ₹2.27 ₹396.68

Rate build-up

TOTAL ₹7,154.36
Add 1 % Water charges on "W" ₹71.54
TOTAL ₹7,225.90
Add GST on "X" (multiplying factor 0.2127) ₹1,536.95
TOTAL ₹8,762.85
Add 15% CPOH on "Y" ₹1,314.43
TOTAL ₹10,077.28
Add Cess @ 1% on "Z" ₹100.77
Cost for 10 sqm. ₹10,178.05
Cost for 1 sqm. ₹1,017.81
Say ₹1,017.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook