CPWD DSR item 16.63 rate analysis

Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-in-charge.

Published rate₹558.30DSR 2023
Rate analysis

Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-in-charge.

DSR rate₹558.30as per item analysis
Item code
16.63
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
4358

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm.
METERIAL
0287 Brick Aggregate (Single size) : 40 mm nominal size cum 1 ₹700.00 ₹700.00
2260 Carriage of Brick aggregate cum 1 ₹0.00 ₹0.00
6501 Sand zone V (Jamuna) cum 0.08 ₹1,320.00 ₹105.60
2335 Carriage of Jamuna sand cum 0.08 ₹0.00 ₹0.00
Labour for spreading, ramming and consolidation.
0114 Beldar day 0.35 ₹736.00 ₹257.60
0115 Coolie day 0.26 ₹736.00 ₹191.36
0101 Bhisti day 0.18 ₹816.00 ₹146.88
Cement concrete-1:3:6
4.1.6 Rate as per item no 4.1.6 of SH : Concrete
Work cum 0.5 ₹7,178.75 ₹3,589.38

Rate build-up

TOTAL ₹4,990.82
Add 1 % Water charges on "W-A" ₹14.01
TOTAL ₹5,004.83
Add GST on "X-A" (multiplying factor 0.2127) ₹301.07
TOTAL ₹5,305.90
Add 15% CPOH on "Y-A" ₹257.48
TOTAL ₹5,563.38
Add Cess @ 1% on "Z-A" ₹19.74
Cost for 10 sqm. ₹5,583.12
Cost for 1 sqm. ₹558.31
Say ₹558.30