Rate analysis
Supplying, stacking and Spreading 6 mm thick red bajri, watering and rolling complete including preparation of the surface and rolling.
DSR rate₹24.45per sqm
With road roller/ hand roller
- Item code
- 16.6.1
- Sub-head
- SH 16 · ROAD WORK
- Unit
- sqm
- Source row
- 309
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 6 mm thick and 100 sqm area | |||||
| (A) Supplying and stacking of Red bajri at site. | |||||
| MATERIAL | |||||
| 0304 | Bajri | cum | 0.6 | ₹1,100.00 | ₹660.00 |
| 2311 | Carriage of Red bajri | cum | 0.6 | ₹0.00 | ₹0.00 |
| (B) Spreading of red bajri | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.54 | ₹736.00 | ₹397.44 |
| 0101 | Bhisti | day | 0.54 | ₹816.00 | ₹440.64 |
| Roller charges (one roller does 1860sqm. | |||||
| consolidation per day of 8 hours and uses 18 litres of diesel oil) | |||||
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.054 | ₹3,350.00 | ₹180.90 |
| 0113 | Chowkidar | day | 0.054 | ₹736.00 | ₹39.74 |
Rate build-up
| TOTAL | ₹1,718.72 |
| Add 1 % Water charges on "W" | ₹17.19 |
| TOTAL | ₹1,735.91 |
| Add GST on "X" (multiplying factor 0.2127) | ₹369.23 |
| TOTAL | ₹2,105.14 |
| Add 15% CPOH on "Y" | ₹315.77 |
| TOTAL | ₹2,420.91 |
| Add Cess @ 1% on "Z" | ₹24.21 |
| Cost for 100 sqm. | ₹2,445.12 |
| Cost per sqm. | ₹24.45 |
| Say | ₹24.45 |