DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.5.2 rate analysis

Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete.(payment for brick aggregate and moorum etc. to be made separately) Over burnt (Jhama) brick aggregate 90 mm to 45 mm

Published rate₹879.70DSR 2023
Rate analysis

Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete.(payment for brick aggregate and moorum etc. to be made separately)

DSR rate₹879.70as per item analysis

Over burnt (Jhama) brick aggregate 90 mm to 45 mm

Item code
16.5.2
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
262

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
LABOUR
0114 Beldar day 0.35 ₹736.00 ₹257.60
0115 Coolie day 0.26 ₹736.00 ₹191.36
0101 Bhisti day 0.18 ₹816.00 ₹146.88
Roller charges (one roller does 230cum.
consolidation per day of 8 hours and uses 18 litres of diesel oil)
0003 Hire charges of Diesel Road Roller - 8 to 10 tonne day 0.004 ₹3,350.00 ₹13.40
0113 Chowkidar day 0.004 ₹736.00 ₹2.94
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹618.38
Add 1 % Water charges on "W" ₹6.18
TOTAL ₹624.56
Add GST on "X" (multiplying factor 0.2127) ₹132.84
TOTAL ₹757.40
Add 15% CPOH on "Y" ₹113.61
TOTAL ₹871.01
Add Cess @ 1% on "Z" ₹8.71
Cost for one cum. ₹879.72
Say ₹879.70