Rate analysis
Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete.(payment for brick aggregate and moorum etc. to be made separately)
DSR rate₹879.70as per item analysis
Over burnt (Jhama) brick aggregate 90 mm to 45 mm
- Item code
- 16.5.2
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 262
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.35 | ₹736.00 | ₹257.60 |
| 0115 | Coolie | day | 0.26 | ₹736.00 | ₹191.36 |
| 0101 | Bhisti | day | 0.18 | ₹816.00 | ₹146.88 |
| Roller charges (one roller does 230cum. | |||||
| consolidation per day of 8 hours and uses 18 litres of diesel oil) | |||||
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.004 | ₹3,350.00 | ₹13.40 |
| 0113 | Chowkidar | day | 0.004 | ₹736.00 | ₹2.94 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
Rate build-up
| TOTAL | ₹618.38 |
| Add 1 % Water charges on "W" | ₹6.18 |
| TOTAL | ₹624.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹132.84 |
| TOTAL | ₹757.40 |
| Add 15% CPOH on "Y" | ₹113.61 |
| TOTAL | ₹871.01 |
| Add Cess @ 1% on "Z" | ₹8.71 |
| Cost for one cum. | ₹879.72 |
| Say | ₹879.70 |