Providing and laying semi- dense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge.
25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Drum Type Hot Mix Plant of 60-90 TPH capacity.
Published rate₹275.30per sqm
Rate analysis
Providing and laying semi- dense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge.
DSR rate₹275.30per sqm
25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Drum Type Hot Mix Plant of 60-90 TPH capacity.
Item code
16.56.2
Sub-head
SH 16 · ROAD WORK
Unit
sqm
Source row
3492
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 195 cum (450 tonnes)
Area covered for 25 mm thickness=7800 sqm
MATERIAL
7309
Paving Asphalt VG-30 of approved quality
tonne
22.5
₹41,202.00
₹9,27,045.00
5% of 450 MT = 22.50 MT
2211
Carriage of Tar bitumen
tonne
22.5
₹0.00
₹0.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.50 tonnes
Weight of aggregate = 450 -22.50 =
427.50 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate =427.50/1.5 =285cum
Grading - II/19 mm (Nominal Size)
9.5 - 4.75 mm size = 57% of 285 = 162.45 cum
4.75mm and below = 41% of 285 = 116.85 cum
0296
Stone Aggregate (Single size) : 12.5 mm nominal size
cum
81.225
₹1,400.00
₹1,13,715.00
Qty = 162.45 * 50 /100
0297
Stone Aggregate (Single size) : 10 mm nominal size
cum
81.225
₹1,400.00
₹1,13,715.00
Qty = 162.45 * 50 /100
2903
Stone chippings/ screenings 4.75 mm nominal size
cum
116.85
₹1,600.00
₹1,86,960.00
Qty = 285 * 41 /100
2202
Carriage of Stone aggregate below 40 mm nominal size
cum
279.3
₹0.00
₹0.00
Lime Filler @ 2% ( percentage by weight of aggregate)
0777
Dry hydrated lime (factory made)
quintal
85.5
₹315.00
₹26,932.50
2208
Carriage of Lime
cum
6.63
₹0.00
₹0.00
(consitering density of lime as 1.29 T per cum) V =8.55/1.29 = 6.63 cum
MACHINERY/ HIRE CHARGES:
0076
Drum Type HMP of 60-90 TPH capacity @ 75 tonne per hour actual output
hour
6
₹13,450.00
₹80,700.00
0064
Paver finisher Hydrostatic with sensor control 100 TPH
Add 10 per cent of cost of carriage to cover cost of loading and unloading
—
—
—
₹1,665.00
0055
Smooth Wheeled Roller 8 to 10 tonne
hour
3.9
₹350.00
₹1,365.00
for initial break down rolling.(6*0.65)
0054
Vibratory roller 8 to 10 tonne
hour
3.9
₹700.00
₹2,730.00
for intermediate rolling.(6*0.65)
0056
Tandem Road Roller
hour
3.9
₹1,350.00
₹5,265.00
Finish rolling with 6-8 tonnes smooth wheeled tandem roller.(6*0.65)
LABOUR
0128
Mate
day
0.84
₹816.00
₹685.44
0114
Beldar
day
14
₹736.00
₹10,304.00
working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction for checking line & levels
Rate build-up
TOTAL
₹15,09,331.94
Add 1 % Water charges on "W"
₹15,093.32
TOTAL
₹15,24,425.26
Add GST on "X" (multiplying factor 0.2127)
₹3,24,245.25
TOTAL
₹18,48,670.51
Add 15% CPOH on "Y"
₹2,77,300.58
TOTAL
₹21,25,971.09
Add Cess @ 1% on "Z"
₹21,259.71
Cost for 7800 Sqm
₹21,47,230.80
Cost per sqm
₹275.29
Say
₹275.30
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.