DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.56.1 rate analysis

Providing and laying semi- dense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity.

Published rate₹277.70per sqm
Rate analysis

Providing and laying semi- dense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge.

DSR rate₹277.70per sqm

25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity.

Item code
16.56.1
Sub-head
SH 16 · ROAD WORK
Unit
sqm
Source row
3492

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 195 cum (450 tonnes)
Area covered for 25 mm thickness=7800 sqm
MATERIAL
7309 Paving Asphalt VG-30 of approved quality tonne 22.5 ₹41,202.00 ₹9,27,045.00
5% of 450 MT = 22.50 MT
2211 Carriage of Tar bitumen tonne 22.5 ₹0.00 ₹0.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.50 tonnes
Weight of aggregate = 450 -22.50 =
427.50 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate =427.50/1.5 =285cum
Grading - II/19 mm (Nominal Size)
9.5 - 4.75 mm size = 57% of 285 = 162.45 cum
4.75mm and below = 41% of 285 = 116.85 cum
0296 Stone Aggregate (Single size) : 12.5 mm nominal size cum 81.225 ₹1,400.00 ₹1,13,715.00
Qty = 162.45 * 50 /100
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 81.225 ₹1,400.00 ₹1,13,715.00
Qty = 162.45 * 50 /100
2903 Stone chippings/ screenings 4.75 mm nominal size nominal size cum 116.85 ₹1,600.00 ₹1,86,960.00
Qty = 285 * 41 /100
2202 Carriage of Stone aggregate below 40 mm nominal size nominal size cum 279.3 ₹0.00 ₹0.00
Lime Filler @ 2% ( percentage by weight of aggregate)
0777 Dry hydrated lime (factory made) quintal 85.5 ₹315.00 ₹26,932.50
2208 Carriage of Lime cum 6.63 ₹0.00 ₹0.00
(consitering density of lime as 1.29 T per cum) V =8.55/1.29 = 6.63 cum
MACHINERY/ HIRE CHARGES:
0062 Hot mix Plant -120 TPH capacity hour 3 ₹16,800.00 ₹50,400.00
@75tonne per hour actual output
0063 Hot mix Plant 100 TPH Capacity hour 3 ₹14,550.00 ₹43,650.00
@75tonne per hour actual output
0064 Paver finisher Hydrostatic with sensor control 100 TPH hour 6 ₹1,700.00 ₹10,200.00
@75tonne per hour actual output
0069 Generator 250 KVA hour 6 ₹450.00 ₹2,700.00
0052 Front end loader 1 cum bucket capacity (incl POL) hour 6 ₹1,450.00 ₹8,700.00
Topper 10 tonne capacity (Taken 10km avarage lead)
450x10=4500 tonne km
0053 Tipper -5 Cum tonne km 4,500 ₹3.70 ₹16,650.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading ₹1,665.00
0055 Smooth Wheeled Roller 8 to 10 tonne hour 3.9 ₹350.00 ₹1,365.00
for initial break down rolling.(6*0.65)
0054 Vibratory roller 8 to 10 tonne hour 3.9 ₹700.00 ₹2,730.00
for intermediate rolling.(6*0.65)
0056 Tandem Road Roller hour 3.9 ₹1,350.00 ₹5,265.00
Finish rolling with 6-8 tonnes smooth wheeled tandem roller.(6*0.65)
LABOUR
0128 Mate day 0.84 ₹816.00 ₹685.44
0114 Beldar day 14 ₹736.00 ₹10,304.00
working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction for checking line & levels

Rate build-up

TOTAL ₹15,22,681.94
Add 1 % Water charges on "W" ₹15,226.82
TOTAL ₹15,37,908.76
Add GST on "X" (multiplying factor 0.2127) ₹3,27,113.19
TOTAL ₹18,65,021.95
Add 15% CPOH on "Y" ₹2,79,753.29
TOTAL ₹21,44,775.24
Add Cess @ 1% on "Z" ₹21,447.75
Cost for 7800 Sqm ₹21,66,222.99
Cost per sqm ₹277.72
Say ₹277.70

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook