DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.52X rate analysis

Sub Analysis X for sub analysis item Number 16.52Y

Published rate₹2,665.15DSR 2023
Rate analysis

Sub Analysis X for sub analysis item Number 16.52Y

DSR rate₹2,665.15as per item analysis
Item code
16.52X
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
3156

Cost components

CodeDescriptionUnitQuantityRateAmount
Sub Analysis 16.52X for use in sub analysis of 16.52Y
Details of cost for 1cum of lime Flyash mortar 1:2:3 (lime:2 flyash:3 coarse sand).
MATERIAL
0773 Unslaked lime quintal 1.52 ₹325.00 ₹494.00
1980 Flyash cum 0.48 ₹12.00 ₹5.76
0982 Coarse sand (zone III) cum 0.72 ₹1,450.00 ₹1,044.00
2208 Carriage of Lime cum 0.24 ₹0.00 ₹0.00
2266 Carriage of Surkhi cum 0.48 ₹0.00 ₹0.00
2203 Carriage of Coarse sand cum 0.72 ₹0.00 ₹0.00
LABOUR
Labour for slaking the lime making, lime putty, grinding, measuring, carrying, depositing and mixing.
0114 Beldar day 0.9 ₹736.00 ₹662.40
0101 Bhisti day 0.45 ₹816.00 ₹367.20
9999 Running and upkeep of mortar mill L.S. 26.91 ₹2.27 ₹61.09
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹2,665.14
Cost of 1.00 cum ₹2,665.14
Say ₹2,665.15