Rate analysis
Sub Analysis X for sub analysis item Number 16.52Y
DSR rate₹2,665.15as per item analysis
- Item code
- 16.52X
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 3156
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Sub Analysis 16.52X for use in sub analysis of 16.52Y | |||||
| Details of cost for 1cum of lime Flyash mortar 1:2:3 (lime:2 flyash:3 coarse sand). | |||||
| MATERIAL | |||||
| 0773 | Unslaked lime | quintal | 1.52 | ₹325.00 | ₹494.00 |
| 1980 | Flyash | cum | 0.48 | ₹12.00 | ₹5.76 |
| 0982 | Coarse sand (zone III) | cum | 0.72 | ₹1,450.00 | ₹1,044.00 |
| 2208 | Carriage of Lime | cum | 0.24 | ₹0.00 | ₹0.00 |
| 2266 | Carriage of Surkhi | cum | 0.48 | ₹0.00 | ₹0.00 |
| 2203 | Carriage of Coarse sand | cum | 0.72 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| Labour for slaking the lime making, lime putty, grinding, measuring, carrying, depositing and mixing. | |||||
| 0114 | Beldar | day | 0.9 | ₹736.00 | ₹662.40 |
| 0101 | Bhisti | day | 0.45 | ₹816.00 | ₹367.20 |
| 9999 | Running and upkeep of mortar mill | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹2,665.14 |
| Cost of 1.00 cum | ₹2,665.14 |
| Say | ₹2,665.15 |