DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.43B rate analysis

Annexure ‘B’ to Item number 16.43

Published rate₹1,046.90per cum
Rate analysis

Annexure ‘B’ to Item number 16.43

DSR rate₹1,046.90per cum
Item code
16.43B
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
2780

Cost components

CodeDescriptionUnitQuantityRateAmount
ANALYSIS OF ANNEXTURE 'B' 16.43B (Required in 16.43)
Details of cost for 85.00 cum
STEEL FORM WORK :
Part-I Cost of materials :
Assuming that pavement 30m long 22.5m wide and 0.30m deep having panel size 6.15x4.61x0.30m or 8.50cu. laid in a day of 8 hrs. Hence form work to be provided for 2 days.
MATERIAL
Channel ISJC 300 for 50 slab of size 6.15mx4.61m=22x30.75+2x46.10 =768.70 m
Total for 500 slabs = 768.70mx10=7687.00 m
7687 m @ 33.10 kg/ m = 254440 kg = 2544.40 q
Assuming that channel will become unserviceable after use for 5000 slab (100 times) and salvage value of steel shall fetch 20% of its basic cost. Qty for using once =2544.40*0.80/5000= 0.407q
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.407 ₹5,965.00 ₹2,427.76
2205 Carriage of Steel tonne 0.041 ₹0.00 ₹0.00
Part-II Labour for assembling, errection, dismeritelling and cleaning the shuttering. Assuming that 255 labour for steel shuttering shall be required as compared to timber shuttering. Contact area of 50 slabs of steel shuttering.
Long channel = 11x20x0.30 = 66.00
= 2x45.10x0.30 = 27.06
Total for 500 slabs= 93.06x10=930.60
LABOUR
0103 Blacksmith 2nd class day 28.6 ₹816.00 ₹23,337.60
0114 Beldar day 28.6 ₹736.00 ₹21,049.60
Carriage of steel for extra lead of runway
0114 Beldar day 57.3 ₹736.00 ₹42,172.80

Rate build-up

TOTAL ₹88,987.76
Cost for 85.00 cum ₹88,987.76
Cost per cum. ₹1,046.91
Say ₹1,046.90

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook