DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.43A rate analysis

Annexure ‘A’ to Item number 16.43

Published rate₹449.45per cum
Rate analysis

Annexure ‘A’ to Item number 16.43

DSR rate₹449.45per cum
Item code
16.43A
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
2739

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 8.5 cum.
MATERIAL:
(i) Painting with primer
(i) Construction joint 6.15m. long 30cm deep
6.15x(0.30+0.01)= 1.91sqm.+
(ii) Dummy joints
4.61m long and 10cm deep 10mm wide
4.6 lx(0.10+0.10+0.01) = 0.97 sqm.
= 2.88 sqm.
2.88sqm. @0.26 lit./sqm. = 0.75 lit. +
Add 5% wastage = 0.03
Total =0.78 lit
0316 Bitumen solution primer of approved quality litre 0.78 ₹50.00 ₹39.00
9977 Carriage L.S. 0.91 ₹2.27 ₹2.07
(ii) Joint sealing compound (GradeA) for construction joint 6.15m long 10mm wide 25mm deep.
6.15x2x2.5cm = 3075cucm
For dummy joints
461xl.0xl0cm. = 4610cucm.
Total = 7685 cum
Add 5% wastage = 384 cucm
Total = 8069 cucm
0314 Bitumen hot sealing compound : grade A kilogram 9.68 ₹30.00 ₹290.40
9977 Carriage L.S. 0.91 ₹2.27 ₹2.07
0370 Coal (steam) quintal 0.015 ₹500.00 ₹7.50
9977 Carriage L.S. 0.91 ₹2.27 ₹2.07
LABOUR:
(ii) For applying primer qty. = 2.88 sqm
0123 Mason 1st class day 3 ₹897.00 ₹2,691.00
0131 Painter day 0.1 ₹816.00 ₹81.60
(iii) Labour for heating and filling sealing compound.
0124 Mason 2nd class day 0.25 ₹816.00 ₹204.00
(iv) Beldar for heating, carrying and pouring of bitumen
0114 Beldar day 0.68 ₹736.00 ₹500.48

Rate build-up

Say 8.07 cudm. @1.2kg/cudm = 9.68 kg
TOTAL ₹3,820.19
Cost for 8.5 cum ₹3,820.19
Cost per cum. ₹449.43
Say ₹449.45