DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.39.3 rate analysis

4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) : With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP : 53

Published rate₹528.65per sqm
Rate analysis

4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) :

DSR rate₹528.65per sqm

With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP : 53

Item code
16.39.3
Sub-head
SH 16 · ROAD WORK
Unit
sqm
Source row
2348

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100sqm.
MATERIAL
7739 Modified Bitumen Refinary produced CRMB - 55 tonne 0.479 ₹33,100.00 ₹15,854.90
@56kg. per cum. of aggregate and 128kg. per cum. of sand:
56x2.60=145.6kg. = 0.146t +
128x2.60 = 332.8kg = 0.333t
Total = 0.479 tonne
2914 Solvent kilogram 33.53 ₹32.00 ₹1,072.96
0.70kg.x479=33.53kg.
2342 Carriage of solvent/ Diesel. quintal 0.335 ₹0.00 ₹0.00
2211 Carriage of Tar bitumen tonne 0.479 ₹0.00 ₹0.00
2910 Stone chippings/ screenings 12.5/ 13.2 mm nominal size cum 1.56 ₹1,400.00 ₹2,184.00
2911 Stone chippings/ screenings 10/ 11.2 mm nominal size cum 1.04 ₹1,400.00 ₹1,456.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 2.6 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 2.6 ₹1,450.00 ₹3,770.00
2203 Carriage of Coarse sand cum 2.6 ₹0.00 ₹0.00
Steam coal for heating bitumen @ 2 qunitals per tonne of bitumen = 2x0.479=0.958q
0370 Coal (steam) quintal 0.958 ₹500.00 ₹479.00
2200 Carriage of steam coal tonne 0.096 ₹0.00 ₹0.00
Labour for cleaning road surface, heating bitumen mixing and spreading aggregate :
(a) For cleaning :
0128 Mate day 0.16 ₹816.00 ₹130.56
0114 Beldar day 1.4 ₹736.00 ₹1,030.40
0115 Coolie day 1.4 ₹736.00 ₹1,030.40
(b) For heating bitumen :
0114 Beldar day 1.88 ₹736.00 ₹1,383.68
(c) For cleaning, mixing and spreading pre-mix aggregate :
0130 Mistry day 0.31 ₹897.00 ₹278.07
0114 Beldar day 9.46 ₹736.00 ₹6,962.56
(d) Consolidation charges :
0113 Chowkidar day 0.45 ₹736.00 ₹331.20
0101 Bhisti day 0.18 ₹816.00 ₹146.88
0003 Hire charges of Diesel Road Roller - 8 to 10 tonne day 0.18 ₹3,350.00 ₹603.00
0001 Hire charges of Coaltar Boiler 900 to 1400 litres day 0.3 ₹900.00 ₹270.00
0023 Hot Bitumen mixer 0.5 cum i/c hand cart day 0.03 ₹3,950.00 ₹118.50
(e) Misc :
0364 Wire brush each 0.09 ₹25.00 ₹2.25
(with thick wire)
0365 Soft brush each 0.27 ₹25.00 ₹6.75
9999 Brooms and gunny bags L.S. 5.33 ₹2.27 ₹12.10
9999 Sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹37,159.80
Add 1 % Water charges on "W" ₹371.60
TOTAL ₹37,531.40
Add GST on "X" (multiplying factor 0.2127) ₹7,982.93
TOTAL ₹45,514.33
Add 15% CPOH on "Y" ₹6,827.15
TOTAL ₹52,341.48
Add Cess @ 1% on "Z" ₹523.41
Cost for 100 sqm. ₹52,864.89
Cost per sqm. ₹528.65
Say ₹528.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook