Rate analysis
Supplying and stacking at site.
DSR rate₹872.05as per item analysis
Over burnt (Jhama) brick aggregate 90 mm to 45 mm
- Item code
- 16.3.5
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 54
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 2909 | Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm size | cum | 1 | ₹613.00 | ₹613.00 |
| 2260 | Carriage of Brick aggregate | cum | 1 | ₹0.00 | ₹0.00 |
Rate build-up
| TOTAL | ₹613.00 |
| Add 1 % Water charges on "W" | ₹6.13 |
| TOTAL | ₹619.13 |
| Add GST on "X" (multiplying factor 0.2127) | ₹131.69 |
| TOTAL | ₹750.82 |
| Add 15% CPOH on "Y" | ₹112.62 |
| TOTAL | ₹863.44 |
| Add Cess @ 1% on "Z" | ₹8.63 |
| Cost for 1 cum | ₹872.07 |
| Say | ₹872.05 |