Rate analysis
Supplying and stacking at site.
DSR rate₹798.10as per item analysis
Over burnt (Jhama) brick aggregate 120 mm to 40 mm
- Item code
- 16.3.4
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 54
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 2908 | Over burnt (Jhama) Brick Aggregate: 120 mm to 40 mm size | cum | 1 | ₹561.00 | ₹561.00 |
| 2260 | Carriage of Brick aggregate | cum | 1 | ₹0.00 | ₹0.00 |
Rate build-up
| TOTAL | ₹561.00 |
| Add 1 % Water charges on "W" | ₹5.61 |
| TOTAL | ₹566.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹120.52 |
| TOTAL | ₹687.13 |
| Add 15% CPOH on "Y" | ₹103.07 |
| TOTAL | ₹790.20 |
| Add Cess @ 1% on "Z" | ₹7.90 |
| Cost for 1 cum | ₹798.10 |
| Say | ₹798.10 |