DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.14 rate analysis

Cutting bajri paths and making good the same including supply of extra quantities of brick aggregate, moorum and red bajri required.

Published rate₹284.20per sqm
Rate analysis

Cutting bajri paths and making good the same including supply of extra quantities of brick aggregate, moorum and red bajri required.

DSR rate₹284.20per sqm
Item code
16.14
Sub-head
SH 16 · ROAD WORK
Unit
sqm
Source row
577

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm.
10x0.075=0.75cum.
MATERIAL
Supplying and stacking 50mm brick aggregate at site(extra quantity)
0286 Brick Aggregate (Single size) : 50 mm nominal size cum 0.19 ₹700.00 ₹133.00
2260 Carriage of Brick aggregate cum 0.19 ₹0.00 ₹0.00
Supplying and stacking red bajri at site
16.3.8 Rate as per Item Number 16.3.8 of SH: Road Work cum 0.06 ₹1,564.90 ₹93.89
Supplying and stacking moorum at site
16.3.10 Rate as per Item Number 16.3.10 of SH: Road cum 0.06 ₹768.25 ₹46.10
LABOUR
For cutting, sorting out, spreading and consolidation of aggregate
0114 Beldar day 1.6 ₹736.00 ₹1,177.60
0115 Coolie day 0.8 ₹736.00 ₹588.80

Rate build-up

TOTAL ₹2,039.39
Add 1 % Water charges on "W-A" ₹18.99
TOTAL ₹2,058.38
Add GST on "X-A" (multiplying factor 0.2127) ₹408.04
TOTAL ₹2,466.42
Add 15% CPOH on "Y-A" ₹348.96
TOTAL ₹2,815.38
Add Cess @ 1% on "Z-A" ₹26.75
Cost for 10 sqm. ₹2,842.13
Cost per sqm. ₹284.21
Say ₹284.20

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook