DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.13.1 rate analysis

Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required. bituminous portion

Published rate₹5,032.25per cum
Rate analysis

Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required.

DSR rate₹5,032.25per cum

bituminous portion

Item code
16.13.1
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
499

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.08cum. (road 6 metres wide, 0.6 metre length wise and 0.30m (average depth) volume = 1.08 cum).
MATERIAL
Supplying and stacking stone aggregate 53mm to 24 mm nominal size at site.
16.3.3 Rate as per Item Number 16.3.3 of SH: Road Work cum 0.09 ₹1,842.30 ₹165.81
Supplying and stacking red bajri at site
16.3.8 Rate as per Item Number 16.3.8 of SH: Road Work cum 0.023 ₹1,564.90 ₹35.99
Supplying and stacking moorum at site
16.3.10 Rate as per Item Number 16.3.10 of SH: Road Work cum 0.022 ₹768.25 ₹16.90
2911 Stone chippings/ screenings 10/ 11.2 mm nominal size cum 0.092 ₹1,400.00 ₹128.80
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.092 ₹0.00 ₹0.00
0309 Paving bitumen VG-10 of approved quality tonne 0.011 ₹33,530.00 ₹368.83
2211 Carriage of Tar bitumen tonne 0.011 ₹0.00 ₹0.00
LABOUR
For cutting road and taking out soling and metalling including sorting and screening.
0114 Beldar day 0.96 ₹736.00 ₹706.56
0115 Coolie day 0.48 ₹736.00 ₹353.28
Relaying soling stone 3.6x0.15=0.54cum.
0114 Beldar day 0.24 ₹736.00 ₹176.64
0115 Coolie day 0.24 ₹736.00 ₹176.64
Relaying road metal with extra quantity and consolidation to 0.10m, thickness 3.6x0.10=0.36cum.
0114 Beldar day 0.71 ₹736.00 ₹522.56
0115 Coolie day 0.48 ₹736.00 ₹353.28
0101 Bhisti day 0.1 ₹816.00 ₹81.60
Painting two coats, 3.6sqm. including labour for spreading grit
0114 Beldar day 0.48 ₹736.00 ₹353.28
0115 Coolie day 0.48 ₹736.00 ₹353.28
9999 Barrier, chowkidar, sprayman, mate, etc. L.S. 40.43 ₹2.27 ₹91.78

Rate build-up

TOTAL ₹3,885.23
Add 1 % Water charges on "W-A" ₹36.67
TOTAL ₹3,921.90
Add GST on "X-A" (multiplying factor 0.2127) ₹787.67
TOTAL ₹4,709.57
Add 15% CPOH on "Y-A" ₹673.63
TOTAL ₹5,383.20
Add Cess @ 1% on "Z-A" ₹51.65
Cost for 1.08 cum. ₹5,434.85
Cost per cum. ₹5,032.27
Say ₹5,032.25