DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.72X rate analysis

Scaffolding

Published rate₹9,081.00DSR 2023
Rate analysis

Scaffolding

DSR rate₹9,081.00as per item analysis
Item code
14.72X
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2041

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for area 22.5 x 9.0= 202.50 sqm
MATERIAL
Assuming shuttering material will become unserviceable after use of 40 times
7397 Base jack each 14 ₹155.00 ₹2,170.00
7x2=14 nos
4009 Mild steel tubes hot finished welded type kilogram 3,765.42 ₹72.00 ₹2,71,110.24
40mm dia M.S. Tube
Vertical standard 2.5m length
= 7x2x9x2.5 = 315.00 m
Bracing ledder 1.5m length = 7x2x9x4.0873 = 513.00 m
Side support 6.00m length = 3x2x6.00= 36.00 m
Horizontal support 3.00m length = 18x3x3.00 = 162.00 m
Total = 1026.00m @ 3.67 kg/m = 3765.42 kg
7387 Spigot for standard jointing kg 123.98 ₹44.00 ₹5,455.12
7x2x9 = 126 nos x 0.40m length = 50.40m
50.40m @ 2.46kg/m = 123.98kg
1034 Bolts and nuts upto 300 mm in length quintal 0.378 ₹5,200.00 ₹1,965.60
2x7x2x9 = 252 nos @ 0.15 kg each
= 37.80 kg = 0.378 q
7346 Double coupler each 120 ₹49.00 ₹5,880.00
2x3x2 + 2x18x3 = 120 nos
7398 Challies each 90 ₹834.00 ₹75,060.00
3 nos x 18 lines = 54 nos
Two level plate challies = 2x 18 lines = 36 nos, Total = 90 nos
7399 Cup lock each 1,314 ₹50.00 ₹65,700.00
Vertical standards 5x7x2x9 = 630.00 Nos.
2x18x19 = 684 Nos.
Total =1314 Nos.
Add 10% for maintenance on P ₹42,734.10
Less 25% salvage value on P -₹1,06,835.24
TOTAL (P+Q+R) ₹3,63,239.82
Considering that scaffolding shall be unserviceable after using 40 times

Rate build-up

TOTAL ₹4,27,340.96
cost of using once ₹9,081.00
Say ₹9,081.00