DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.72 rate analysis

Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. Note: - This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done.

Published rate₹338.25per sqm
Rate analysis

Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. Note: - This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done.

DSR rate₹338.25per sqm
Item code
14.72
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
sqm
Source row
2010

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for area 22.5m x 9.0m =202.5 sqm
14.72X Rate as per Item No.14.72X of SH:Repairs to Buildings each 1 ₹9,081.00 ₹9,081.00
2205 Carriage of Steel tonne 6.054 ₹0.00 ₹0.00
40mm dia MS pipe = 3765.42 kg
25mm spigot = 123.98 kg
Nuts & bolts = 37.80 kg
Clamp = 120 nos @ 1.00kg each = 120.00 kg
Challies = 90 nos @ 15.00kg each
= 1350.00 kg
Cup locks = 1314 nos @ 0.50kg each
= 657.00 kg
Total = 6054.20 kg = 6.054 tonne
LABOUR
0116 Fitter (grade 1) day 15.5 ₹897.00 ₹13,903.50
0114 Beldar day 31 ₹736.00 ₹22,816.00
9999 Sundries L.S. 1,035 ₹2.27 ₹2,349.45

Rate build-up

TOTAL ₹48,149.95
Add 1 % Water charges on "W" ₹481.50
TOTAL ₹48,631.45
Add GST on "X" (multiplying factor 0.2127) ₹10,343.91
TOTAL ₹58,975.36
Add 15% CPOH on "Y" ₹8,846.30
TOTAL ₹67,821.66
Add Cess @ 1% on "Z" ₹678.22
Cost of 202.50 sqm. ₹68,499.88
Cost of 1 sqm. ₹338.27
Say ₹338.25

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook