Rate analysis
Making the opening in brick masonry including dismantling in floor or walls by cutting masonry and making good the damages to walls, flooring and jambs complete, to match existing surface i/c disposal of mulba/ rubbish to the nearest municipal dumping ground, all complete as per direction of Engineer-in-Charge.
DSR rate₹1,264.35as per item analysis
For door/ window/ clerestory window
- Item code
- 14.4.1
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 190
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one opening of size 0.90x2.10m = 1.89 sqm | |||||
| Cement mortar 1:6 (1 cement: 6 fine sand) | |||||
| 3.6 | Rate as per Item Number 3.6 of SH: Mortars | cum | 0.01 | ₹3,038.50 | ₹30.39 |
| 9999 | Cement concrete 1:2:4 filled in chase cut | L.S. | 24.57 | ₹2.27 | ₹55.77 |
| 0124 | Mason 2nd class | day | 0.5 | ₹816.00 | ₹408.00 |
| 0114 | Beldar | day | 1.2 | ₹736.00 | ₹883.20 |
| 0115 | Coolie | day | 0.4 | ₹736.00 | ₹294.40 |
| 9999 | Scaffolding and Sundries | L.S. | 3.5 | ₹2.27 | ₹7.95 |
Rate build-up
| TOTAL | ₹1,679.71 |
| Add 1 % Water charges on "W" | ₹16.80 |
| TOTAL | ₹1,696.51 |
| Add GST on "X" (multiplying factor 0.2127) | ₹360.85 |
| TOTAL | ₹2,057.36 |
| Add 15% CPOH on "Y" | ₹308.60 |
| TOTAL | ₹2,365.96 |
| Add Cess @ 1% on "Z" | ₹23.66 |
| Cost of 1.89sqm. | ₹2,389.62 |
| Cost of 1.00 sqm. | ₹1,264.35 |
| Say | ₹1,264.35 |