DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.13 rate analysis

Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge.

Published rate₹696.05DSR 2023
Rate analysis

Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge.

DSR rate₹696.05as per item analysis
Item code
14.13
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
504

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
(i) Dismantling tiles/bricks in cement mortar including removing mud plaster and cleaning the tiles/bricks
LABOUR
0155 Mason (average) day 0.54 ₹857.00 ₹462.78
0114 Beldar day 0.54 ₹736.00 ₹397.44
(ii) Preparing the surface, for mud phuska to proper slope, relaying mud plaster gobri leeping.
0155 Mason (average) day 0.27 ₹857.00 ₹231.39
25mm thick mud plaster including gobri leaping
MATERIAL
Mud mortar
3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.24 ₹940.55 ₹225.73
0308 Bhusa quintal 0.084 ₹530.00 ₹44.52
Gobri mortar
3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.12 ₹940.55 ₹112.87
LABOUR
0114 Beldar day 0.25 ₹736.00 ₹184.00
(iii) relaying tiles/bricks including Cement mortar 1:3 (1 Cement : 3 fine sand) for grouting
3.3 Rate as per item No 3.3 of SH: Mortars cum 0.061 ₹4,379.05 ₹267.12
LABOUR
0155 Mason (average) day 1.2 ₹857.00 ₹1,028.40
0114 Beldar day 1.5 ₹736.00 ₹1,104.00
0101 Bhisti day 1 ₹816.00 ₹816.00
9999 Disposal of mulba L.S. 5.33 ₹2.27 ₹12.10
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹4,892.55
Add 1 % Water charges on "W" ₹48.93
TOTAL ₹4,941.48
Add GST on "X" (multiplying factor 0.2127) ₹1,051.05
TOTAL ₹5,992.53
Add 15% CPOH on "Y" ₹898.88
TOTAL ₹6,891.41
Add Cess @ 1% on "Z" ₹68.91
Cost of 10.00 sqm ₹6,960.32
Cost of 1.00 sqm ₹696.03
Say ₹696.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook