DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.73.1 rate analysis

Forming groove of uniform size in the top layer of washed stone grit plaster as per approved pattern using wooden battens, nailed to the under layer, including removal of wooden battens, repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge : 15 mm wide and 15 mm deep groove

Published rate₹75.15DSR 2023
Rate analysis

Forming groove of uniform size in the top layer of washed stone grit plaster as per approved pattern using wooden battens, nailed to the under layer, including removal of wooden battens, repair to the edges of panels and finishing the groove complete as per specifications and direction of the Engineer-in-charge :

DSR rate₹75.15as per item analysis

15 mm wide and 15 mm deep groove

Item code
13.73.1
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
2541

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 30 mtrs
Second class kail wood in plank 30 x0.015 x0.015m =6.75cudm
Wastage @ 10% = 0.68
Total = 7.43 cudm
Assuming that the battens shall become unserviceable after using 5 times
MATERIAL
1198 Second class kail wood in planks 10 cudm 0.148 ₹260.00 ₹38.48
9977 Carriage of wood L.S. 0.39 ₹2.27 ₹0.89
Labour for making battens
0112 Carpenter 2nd class day 0.15 ₹816.00 ₹122.40
0114 Beldar day 0.15 ₹736.00 ₹110.40
9999 Sundries L.S. 2.86 ₹2.27 ₹6.49
Labour for nailing the battens to under layer and finishing and repairing grooves
0123 Mason 1st class day 0.7 ₹897.00 ₹627.90
0114 Beldar day 0.7 ₹736.00 ₹515.20
9999 Nails and cement mortar L.S. 71.76 ₹2.27 ₹162.90

Rate build-up

Cost for using once = 7.43 / 5 = 1.48 cudm
TOTAL ₹1,584.66
Add 1 % Water charges on "W" ₹15.85
TOTAL ₹1,600.51
Add GST on "X" (multiplying factor 0.2127) ₹340.43
TOTAL ₹1,940.94
Add 15% CPOH on "Y" ₹291.14
TOTAL ₹2,232.08
Add Cess @ 1% on "Z" ₹22.32
Cost of 30.00 mtrs ₹2,254.40
Cost of 1.00 metre ₹75.15
Say ₹75.15