DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.59 rate analysis

Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively.

Published rate₹66.90DSR 2023
Rate analysis

Coal tarring two coats on new work using 0.16 Litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively.

DSR rate₹66.90as per item analysis
Item code
13.59
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
2180

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
9999 Lime L.S. 1.43 ₹2.27 ₹3.25
0324 Coal Tar litre 2.8 ₹35.00 ₹98.00
9977 Carriage of material L.S. 1.43 ₹2.27 ₹3.25
0771 Kerosene oil litre 0.5 ₹50.00 ₹25.00
LABOUR
0114 Beldar day 0.43 ₹736.00 ₹316.48
9999 Brushes etc L.S. 5.33 ₹2.27 ₹12.10
9999 Sundries L.S. 5.33 ₹2.27 ₹12.10

Rate build-up

TOTAL ₹470.18
Add 1 % Water charges on "W" ₹4.70
TOTAL ₹474.88
Add GST on "X" (multiplying factor 0.2127) ₹101.01
TOTAL ₹575.89
Add 15% CPOH on "Y" ₹86.38
TOTAL ₹662.27
Add Cess @ 1% on "Z" ₹6.62
Cost of 10.00 sqm ₹668.89
Cost of 1.00 sqm ₹66.89
Say ₹66.90