DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.110.2 rate analysis

Old work (One or more coats) applied @ 1.82 ltr/10 sqm.

Published rate₹109.10DSR 2023
Rate analysis

Old work (One or more coats) applied @ 1.82 ltr/10 sqm.

DSR rate₹109.10as per item analysis
Item code
13.110.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
3694

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
8507 Textured exterior paint litre 1.82 ₹185.00 ₹336.70
9977 Carriage of material L.S. 0.52 ₹2.27 ₹1.18
LABOUR
0131 Painter day 0.33 ₹816.00 ₹269.28
0115 Coolie day 0.17 ₹736.00 ₹125.12
9999 Brushes, sand paper etc L.S. 7.15 ₹2.27 ₹16.23
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹766.81
Add 1 % Water charges on "W" ₹7.67
TOTAL ₹774.48
Add GST on "X" (multiplying factor 0.2127) ₹164.73
TOTAL ₹939.21
Add 15% CPOH on "Y" ₹140.88
TOTAL ₹1,080.09
Add Cess @ 1% on "Z" ₹10.80
Cost of 10.00 sqm ₹1,090.89
Cost of 1.00 sqm ₹109.09
Say ₹109.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook