DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.9 rate analysis

Extra for straight cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated, semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter for chimney stacks, skylights etc.

Published rate₹92.95DSR 2023
Rate analysis

Extra for straight cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated, semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter for chimney stacks, skylights etc.

DSR rate₹92.95as per item analysis
Item code
12.9
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
570

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3 metres of periphery
Area of cutting 0.9mx0.6m=0.54sqm.
Perimeter = 3 metres
LABOUR
0111 Carpenter 1st class day 0.12 ₹897.00 ₹107.64
0114 Beldar day 0.12 ₹736.00 ₹88.32

Rate build-up

TOTAL ₹195.96
Add 1 % Water charges on "W" ₹1.96
TOTAL ₹197.92
Add GST on "X" (multiplying factor 0.2127) ₹42.10
TOTAL ₹240.02
Add 15% CPOH on "Y" ₹36.00
TOTAL ₹276.02
Add Cess @ 1% on "Z" ₹2.76
Cost of 3.00 metres of periphery ₹278.78
Cost of 1.00 metre of periphery ₹92.93
Say ₹92.95