DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.56 rate analysis

Providing and laying roof insulation with 40 mm thick impervious sprayed, closed cell free Rigid Polyurethane foam over deck insulation conforming to IS - 12432 Pt. III (density of foam being 40-45 kg/ cum), over a coat of polyurethane primer applied @ 6-8 sqm per litre, laying 400 G polythene sheet over PUF spray and providing a wearing course of 40 mm thick cement screed 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 20 mm nominal size) in chequered rough finish, in panels of 2.5 m x 2.5 m and embedding with 24 G wire netting and sealing the joints with polymerized mastic, all complete as per direction of Engineer-in-Charge.

Published rate₹1,570.00per sqm
Rate analysis

Providing and laying roof insulation with 40 mm thick impervious sprayed, closed cell free Rigid Polyurethane foam over deck insulation conforming to IS - 12432 Pt. III (density of foam being 40-45 kg/ cum), over a coat of polyurethane primer applied @ 6-8 sqm per litre, laying 400 G polythene sheet over PUF spray and providing a wearing course of 40 mm thick cement screed 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 20 mm nominal size) in chequered rough finish, in panels of 2.5 m x 2.5 m and embedding with 24 G wire netting and sealing the joints with polymerized mastic, all complete as per direction of Engineer-in-Charge.

DSR rate₹1,570.00per sqm
Item code
12.56
Sub-head
SH 12 · ROOFING
Unit
sqm
Source row
3234

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 sqm
MATERIAL
7050 PU Primer sqm 1 ₹54.00 ₹54.00
Area for PU Spray = 1 sqm+
Add for wastage @ 10%=0.10 sqm
Total=1.10 sqm
7051 40 mm (average) PU spray having 40-45 kg/m3 density sqm 1.1 ₹385.00 ₹423.50
7052 GI wire netting 3/4" x 24 G sqm 1 ₹28.00 ₹28.00
9999 Sundries L.S. 6.71 ₹2.27 ₹15.23
9999 Polymerized mastic for all joints L.S. 20.13 ₹2.27 ₹45.70
7053 400 G polythene sheet sqm 1 ₹13.00 ₹13.00
9999 Cement L.S. 44.67 ₹2.27 ₹101.40
9999 Graded stone L.S. 13.75 ₹2.27 ₹31.21
9999 Sand L.S. 21.48 ₹2.27 ₹48.76
9977 Carriage of material L.S. 16.78 ₹2.27 ₹38.09
LABOUR
9999 For PU spray L.S. 80.54 ₹2.27 ₹182.83
9999 For cement screed with Polythene sheet L.S. 53.69 ₹2.27 ₹121.88

Rate build-up

TOTAL ₹1,103.60
Add 1 % Water charges on "W" ₹11.04
TOTAL ₹1,114.64
Add GST on "X" (multiplying factor 0.2127) ₹237.08
TOTAL ₹1,351.72
Add 15% CPOH on "Y" ₹202.76
TOTAL ₹1,554.48
Add Cess @ 1% on "Z" ₹15.54
Cost of 1 sqm ₹1,570.02
Say ₹1,570.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook