DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.55 rate analysis

Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner.

Published rate₹1,703.95per sqm
Rate analysis

Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI (solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts complete, including providing skirting upto 150 mm height along the parapet walls in the same manner.

DSR rate₹1,703.95per sqm
Item code
12.55
Sub-head
SH 12 · ROOFING
Unit
sqm
Source row
3201

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm
Area= 10 sqm+
Add wastage @ 3%=0.3 sqm
Total=10.30 sqm
MATERIAL
1204 Precast heat resistant terrace tiles (size 300x300mm) and 20mm thick sqm 10.3 ₹465.00 ₹4,789.50
Cement mortar 1:4 (1 cement : 4 coarse sand)
3.9 Rate as per Item No.3.9 of SH:Mortar cum 0.224 ₹4,211.70 ₹943.42
0367 Portland Cement (OPC-43 grade) tonne 0.044 ₹5,156.00 ₹226.86
0368 White Cement tonne 0.044 ₹10,500.00 ₹462.00
2209 Carriage of Cement tonne 0.088 ₹0.00 ₹0.00
0875 Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigment kilogram 3.08 ₹65.00 ₹200.20
LABOUR
0124 Mason 2nd class day 1.6 ₹816.00 ₹1,305.60
0115 Coolie day 2 ₹736.00 ₹1,472.00
0139 Skilled Beldar (for floor rubbing etc.) day 1 ₹816.00 ₹816.00
0101 Bhisti day 1 ₹816.00 ₹816.00
0013 Machine for rubbing of floors day 1.6 ₹350.00 ₹560.00
9999 Sundries including carborandum stone etc. L.S. 169.98 ₹2.27 ₹385.85

Rate build-up

TOTAL ₹11,977.43
Add 1 % Water charges on "W" ₹119.77
TOTAL ₹12,097.20
Add GST on "X" (multiplying factor 0.2127) ₹2,573.07
TOTAL ₹14,670.27
Add 15% CPOH on "Y" ₹2,200.54
TOTAL ₹16,870.81
Add Cess @ 1% on "Z" ₹168.71
Cost of 10 sqm ₹17,039.52
Cost of 1 sqm ₹1,703.95
Say ₹1,703.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook