Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J, or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete : 1.60 mm thick with zinc coating not less than 350 gm/m²

Published rate₹1,863.90DSR 2023
Rate analysis

Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J, or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete :

DSR rate₹1,863.90as per item analysis

1.60 mm thick with zinc coating not less than 350 gm/m²

Item code
12.5.1
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
384

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 9.325m
MATERIAL
G.I. plain sheets 2.5x0.9m
4 nos. @ 29.95Kg/sheet =119.80Kg.+
Add 2% wastage = 2.40Kg.
Total = 122.20 kg. or 1.222q.
0992 Galvanised steel plain sheets quintal 1.222 ₹6,800.00 ₹8,309.60
2302 Carriage of G.I. sheet and accessories tonne 0.12 ₹0.00 ₹0.00
0222 Seam bolts and nuts 6 mm dia and 25 mm long 10 Nos 1.2 ₹11.00 ₹13.20
25mmx6mm (There are 14 joints)
1211 G.I. plain washer for seam bolts 100 Nos 0.12 ₹32.00 ₹3.84
1208 Bitumen washer 100 Nos 0.12 ₹30.00 ₹3.60
9977 Carriage of bolts, nuts and washers L.S. 0.91 ₹2.27 ₹2.07
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69
LABOUR
0130 Mistry day 0.4 ₹897.00 ₹358.80
0102 Blacksmith 1st class day 1.2 ₹897.00 ₹1,076.40
0103 Blacksmith 2nd class day 0.8 ₹816.00 ₹652.80
0114 Beldar day 2.4 ₹736.00 ₹1,766.40

Rate build-up

TOTAL ₹12,217.40
Add 1 % Water charges on "W" ₹122.17
TOTAL ₹12,339.57
Add GST on "X" (multiplying factor 0.2127) ₹2,624.63
TOTAL ₹14,964.20
Add 15% CPOH on "Y" ₹2,244.63
TOTAL ₹17,208.83
Add Cess @ 1% on "Z" ₹172.09
Cost of 9.325 metres ₹17,380.92
Cost of 1.00 metre ₹1,863.91
Say ₹1,863.90