DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.21.1 rate analysis

Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design : In 75x75 mm deep chase

Published rate₹305.15DSR 2023
Rate analysis

Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10 mm and down gauge), including finishing with cement mortar 1:3 (1 cement : 3 fine sand) as per standard design :

DSR rate₹305.15as per item analysis

In 75x75 mm deep chase

Item code
12.21.1
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
1184

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metre cement concrete
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 0.836 ₹1,400.00 ₹1,170.40
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.836 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 0.418 ₹1,450.00 ₹606.10
2203 Carriage of Coarse sand cum 0.418 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.3 ₹5,156.00 ₹1,546.80
2209 Carriage of Cement tonne 0.3 ₹0.00 ₹0.00
0114 Beldar day 0.85 ₹736.00 ₹625.60
0115 Coolie day 0.56 ₹736.00 ₹412.16
0101 Bhisti day 0.25 ₹816.00 ₹204.00
0123 Mason 1st class day 0.05 ₹897.00 ₹44.85
0124 Mason 2nd class day 0.05 ₹816.00 ₹40.80
0128 Mate day 0.037 ₹816.00 ₹30.19
9999 Hire and running charge of mechanical mixer L.S. 24.7 ₹2.27 ₹56.07
9999 Sundries L.S. 13 ₹2.27 ₹29.51
0123 Mason 1st class day 1.5 ₹897.00 ₹1,345.50
0124 Mason 2nd class day 1.5 ₹816.00 ₹1,224.00
9999 Sundries L.S. 50.7 ₹2.27 ₹115.09
0123 Mason 1st class day 2.5 ₹897.00 ₹2,242.50
0124 Mason 2nd class day 2.5 ₹816.00 ₹2,040.00
0114 Beldar day 10 ₹736.00 ₹7,360.00
9977 Carriage L.S. 80.6 ₹2.27 ₹182.96
Cement mortar for grouting 1:3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.09 ₹4,379.05 ₹394.11
0155 Mason (average) day 0.81 ₹857.00 ₹694.17
0115 Coolie day 1.01 ₹736.00 ₹743.36
0101 Bhisti day 0.33 ₹816.00 ₹269.28
9999 Hire and running charges of mechanical mixer L.S. 16.9 ₹2.27 ₹38.36
9999 Sundries L.S. 14.3 ₹2.27 ₹32.46

Rate build-up

TOTAL ₹21,448.27
Add 1 % Water charges on "W" ₹214.48
TOTAL ₹21,662.75
Add GST on "X" (multiplying factor 0.2127) ₹4,607.67
TOTAL ₹26,270.42
Add 15% CPOH on "Y" ₹3,940.56
TOTAL ₹30,210.98
Add Cess @ 1% on "Z" ₹302.11
Cost of 100 metre ₹30,513.09
Cost of 1.00 metre ₹305.13
Say ₹305.15